Beacon Data Centers
Data-centre developer founded in 2023 by New York venture firm Nadia Partners.
As of November 2026, Beacon Data Centers has Alberta regulatory approval, granted on 17 November, for a 1,494 MW power plant serving its proposed hyperscale data centre near Calgary, though the data centre still lacks a county permit.
Last refreshed: 26 November 2026 · Appears in 1 active topic
Can Beacon build its Calgary data centre while the county pauses permits?
Timeline for Beacon Data Centers
Won approval for its data-centre power plant through a subsidiary
Data Centres: Boom and Backlash: Alberta clears a plant Bill 42 would barBackground
Beacon Data Centers is a data-centre developer founded in 2023 by Nadia Partners, a New York venture firm. Its Alberta project is a proposed hyperscale data centre in Rocky View County, just outside Calgary.
Beacon won provincial approval on 17 November 2026 for the 1,494 MW plant that would power the site. Bill 42, tabled by minister Nate Glubish a day later, targets plants on prime farmland and near homes, but its carve-out for approved schemes leaves Beacon's plant untouched.
The approval covers power, not the campus. The data centre still needs a permit from the county before it can be built, which leaves the project's next step with local government rather than the province.
Who owns Beacon Data Centers?
What did Alberta approve for Beacon Data Centers near Calgary?
Where is Beacon's data centre near Calgary?
Why is Beacon's Calgary project exempt from Alberta's Bill 42?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.