Rocky View County
Alberta municipality bordering Calgary; site of the 1,494 MW plant approved for a data centre.
As of November 2026, Rocky View County holds the last local say over a data centre near Calgary, after Alberta's utilities regulator approved its 1,494 MW power plant on 17 November while the campus still lacks a county permit.
Last refreshed: 26 November 2026 · Appears in 1 active topic
Alberta approved a 1,494 MW plant here; can Rocky View still block the data centre?
Timeline for Rocky View County
Kept a moratorium on data-centre permits
Data Centres: Boom and Backlash: Alberta clears a plant Bill 42 would barBackground
Rocky View County is a rural municipality in Alberta on the edge of Calgary. It issues the local land-use permits that any data-centre campus on its territory needs, which makes it a checkpoint for projects that bring their own power.
That role came into focus on 17 November 2026, when provincial regulators cleared a 1,494 MW power plant meant to supply a proposed data centre in the county. The plant has its provincial approval; the data centre still needs the county's.
The province moved a day later. A minister tabled Bill 42, which would bar such plants from prime farmland and from sites close to homes. It exempts projects the Commission has already approved or is considering, so it would not stop this one. The open decision on the site therefore rests with the county.
What is Rocky View County's data-centre moratorium?
Where is the Rocky View data-centre power plant?
Why could Alberta's regulator approve a plant Rocky View has not permitted?