Microsoft quits Nscale's Essex AI site

3 min read
00:06UTC

Microsoft pulled out of its anchor deal at Nscale's Loughton site after UK Power Networks warned grid capacity might not arrive until the 2030s.

TechnologyDeveloping
Key takeaway

Microsoft left Loughton because UK transmission capacity may not reach Essex until the 2030s.

Microsoft has withdrawn from its anchor agreement at Nscale's planned artificial intelligence (AI) data centre at Loughton in Essex, after UK Power Networks warned that grid capacity might not be available until the 2030s⁠1. The Telegraph reported the exit on 18 October, and Microsoft confirmed on 19 October that the withdrawal covers only Loughton⁠2.

Nscale, a UK AI cloud company, announced Loughton in September 2025 as a 50 MW site, expandable to 90 MW, holding 23,040 of Nvidia's GB300 chips, graphics processors (GPUs) built for AI work. First chips were due in early 2027 for Microsoft's Azure cloud. UK Power Networks runs the local lines and substations for London and the east and south-east of England; it says many data centres are waiting on transmission works, the high-voltage network upstream, which it does not own.

Nscale says it remains "committed to both the Loughton project and the UK" and is "exploring alternative power sources for the site". The company, which is preparing a New York listing reportedly valued at up to US$35bn, says the grid problem is London-wide and touches no other contract. Ministers created GB Grid in September so businesses can build and co-fund their own connections, but GB Grid does not touch transmission, where Loughton's wait sits.

Deep Analysis

In plain English

Nscale is a British company that builds data centres for artificial intelligence (AI): buildings packed with powerful computer chips. Microsoft had agreed to be the main customer at a planned Nscale site in Loughton, Essex. UK Power Networks, the company that runs local power lines in London and the south-east, warned that it might not be able to supply enough electricity until the 2030s. The bigger high-voltage lines that feed its network need upgrading first, and it does not own those. Without a date for power, Microsoft walked away from this site. Nscale says it still wants to build there and is looking at other ways to get electricity.

Deep Analysis
Root Causes

Connection offers in Great Britain have been handed out largely in order of application. Contracted offers in the demand queue reached 125 GW by mid-2025, up from 41 GW in November 2024. Speculative and real projects sit in the same line, so a ready project can wait behind ones that may never build.

Ownership adds a second cause. UK Power Networks runs local lines and substations, but the reinforcement Loughton needs sits upstream on the transmission network. The company that tells a developer its date does not control the works that set it.

What could happen next?
  • Consequence

    Nscale needs a new anchor customer or on-site power before Loughton can proceed.

    Short term · Assessed
  • Risk

    Investors in Nscale's planned New York listing may test the power dates at its other UK sites.

    Short term · Suggested
  • Meaning

    In England the binding constraint on AI sites is upstream transmission, not the site or the buyer.

    Medium term · Assessed
First Reported In

Update #17 · Stalled power line cuts A$140m from NEXTDC guidance

The Register· 22 Oct 2026
Read original →
Causes and effects
This Event
Microsoft quits Nscale's Essex AI site
A hyperscaler walked away from a UK AI site over the wait for transmission capacity, which no single developer or distributor can speed up.
Different Perspectives
Business Model Analyst
Business Model Analyst
The business-analysis website argued on 24 November 2026 that Agon's $450m valuation runs ahead of its sales, because defence procurement sets how fast it can sell. Two state funds bought into Agon at that price and published neither amount.
Tony Blair Institute
Tony Blair Institute
The think tank, in a report covered on 29 October 2026, called for a £100m-a-year state fund for research startups and a 5% benchmark for university stakes in spinouts. It is the case for more public money in spinouts, made weeks before the British Business Bank took a £43m stake in OSE, Oxford's spinout investor.
Centre for Policy Studies
Centre for Policy Studies
The free-market think tank argued on 22 October 2026 that the state's investment bodies, the British Business Bank among them, cost up to £2bn a year net in their early years. It wants new commitments capped, and this week's £43m OSE stake and €75m Plural commitment are the kind of new Bank money it would cap.
Invest NI
Invest NI
Northern Ireland's development agency backed three technology expansions between 19 and 23 November, including hubs for QCP and Insight Marine that will create 27 jobs between them. None was a funding round, so its support was measured in jobs and premises rather than equity.
NATO
NATO
NATO's STARLIFT plan, which Britain and ten other countries signed, the Ministry of Defence said on 22 November, sets out a network of launch sites using commercial firms. It came with no money or contract, so SaxaVord and British launch companies gain a framework to bid into, not orders.
Sequoia Capital
Sequoia Capital
Sequoia co-led Isomorphic Labs' $5bn Series C on 17 November, 13 days after saying it would close its London office and back European founders from the Bay Area. British founders now pitch its partners in California, while its money still leads the largest London rounds.