European Energy Markets
27JUL

Capacity law faces 24 June hearing

4 min read
09:24UTC

Germany's StromVKG capacity-market law goes to a public expert hearing on 24 June, with a Greens motion and Federal Cartel Office concerns in play before the first 4.5 GW auction targeted for 1 September.

EconomicDeveloping
Key takeaway

The 24 June hearing decides whether the 1 September capacity auction date holds.

The StromVKG, Germany's electricity capacity-market law, goes to a public expert Anhoerung (hearing) at the Paul-Loebe-Haus on 24 June 1. A capacity market pays plants to be available rather than for the power they sell, the instrument Germany is using to keep dispatchable gas capacity on the system as renewables grow.

The Greens motion 21/6369 demands technology-neutral auction criteria and clarity on how the levy is financed , carrying forward the hydrogen-conversion push the group raised in committee on 17 June. The Federal Cartel Office, Germany's competition authority, has flagged market-concentration concerns in the design. The bill reached this stage after the Bundestag's first reading and committee referral advanced it under accelerated procedure .

The first 4.5 GW long-duration auction is targeted for 1 September, a second 4.5 GW for 8 December, with a ten-hour continuous-output rule that excludes batteries from the opening tranche. That rule is the design choice with the sharpest market consequence: it hands the first auctions to long-duration thermal plant and shuts storage out of the initial capacity payments.

The hearing is where the 1 September date either holds or slips. The timing connects directly to the spark: CCGTs that have just turned profitable to run are the same plants the capacity auctions are meant to underwrite, so any delay leaves their forward economics resting on the spread alone.

Deep Analysis

In plain English

Germany is creating a capacity market: a system to pay gas power stations to stay available as a backup for when wind and solar are not generating enough electricity. The law establishing it, the StromVKG, passed its first parliamentary reading in June 2026. On 24 June, the German parliament held a public hearing on the StromVKG design. The Greens party wants the rules to be technology-neutral, asking that batteries and other clean technologies also be eligible for capacity payments, rather than gas stations alone. Second, Germany's competition watchdog, the Federal Cartel Office, is worried that the programme would mostly pay money to a small number of big energy companies that already own most of the gas power stations. The first auction is planned for 1 September 2026, with a second in December. Whether those dates hold depends on what comes out of the hearing on 24 June.

What could happen next?
  • Risk

    A successful legal challenge to the ten-hour battery exclusion rule, via either a Cartel Office formal proceeding or an EU Commission state-aid opening, would delay the September auction and leave Germany without the capacity mechanism framework through the current heating season.

    Short term · Suggested
  • Consequence

    If the September auction proceeds on schedule and awards contracts to existing CCGT plant, the gas power stations currently generating at +EUR 30 spark spread receive both a market margin and a capacity payment; double compensation that the Cartel Office's concentration concern addresses.

    Medium term · Assessed
  • Precedent

    Germany's battery exclusion replicates the UK T-4 2014 design error; the EU Commission is likely to require technology-neutral admission within two to three years as occurred in the UK.

    Long term · Assessed
First Reported In

Update #20 · Spark spread now feeds the winter deficit

Deutscher Bundestag· 22 Jun 2026
Read original
Different Perspectives
Slovakia
Slovakia
Slovakia says it dropped its hold-out on the 21st sanctions package only after Ursula von der Leyen personally signed written gas-price and supply guarantees. The Council of the European Union's own 17,238-character release on the package names neither Slovakia nor any guarantee, leaving Bratislava's account unconfirmed by the institutional record.
EU regulator on capacity mechanisms
EU regulator on capacity mechanisms
Brussels is watching Germany's StromVKG first 4.5 GW capacity auction move toward its 8 September bid deadline without a resolved state-aid clearance for the 9 GW 2026 programme's gas-plant subsidies. A negative spark spread this deep on cheap gas strengthens the case for subsidised dispatchable capacity, the same case still awaiting a state-aid ruling.
French power exporters
French power exporters
French day-ahead cleared EUR 41.13/MWh on Sunday 26 July, EUR 43.09 below Germany, on wind more than doubling and a demand trough, not on any nuclear recovery. The desk expects the discount to hold only as long as French wind and weekend demand repeat, not as a durable nuclear-cost advantage.
European gas storage operator
European gas storage operator
A storage operator stopped bidding for prompt TTF cargoes on 21 July, reading the strike-halt unwind as the start of a fuel-side correction rather than a floor. It expects the gap between prompt and forward gas to keep narrowing as the war premium continues leaving the curve.
German gas-fired power fleet
German gas-fired power fleet
German gas-fired plants cut output from 4.37 GW to 2.85 GW between 24 and 27 July, even as TTF fell 8 per cent, because below roughly minus EUR 40/MWh the fuel price stopped deciding dispatch. The fleet expects no relief until wind eases or StromVKG's first 4.5 GW auction adds capacity.
French industrial power consumers
French industrial power consumers
France's day-ahead discount to Germany has nearly closed as TTF and EUA rise together on both sides of the border, eroding the arbitrage French industry relied on through the summer. A standing negative spark removes the German demand buffer that kept that spread wide.