The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether **Microsoft**, **Alphabet**, **Amazon** and **Meta** preserve their raised 2026 capex guidance through the late-July Q2 earnings cycle now that OpenAI's compute commitment has been visibly trimmed.
From the 16 May briefing · Deadline: late-July
Whether **FERC** publishes the RM26-4-000 NOPR (Notice of Proposed Rulemaking) by end-June, and whether PJM's 18 May filing matches the language FERC accepted on 16 April.
From the 16 May briefing · Deadline: 18 May
Whether the 18-21 May Denver, Seattle and Minneapolis votes produce a majority of refusals, consolidating the municipal moratorium tier into a default posture.
From the 16 May briefing · Deadline: 21 May
Whether OpenAI's pivot to leased compute reroutes Q3 hyperscaler bookings toward **Equinix**, **Digital Realty** and other colocation operators, and whether Crusoe's Abilene inventory finds a second taker.
From the 16 May briefing
The **FERC RM26-4-000** order at end of June: whether it constrains or accelerates large-load interconnection, and how it treats behind-the-meter cost allocation
From the 6 May briefing · Deadline: end of June
Whether any second US state attempts a moratorium after the Maine veto, and whether the Sanders-Ocasio-Cortez federal proposal reaches a committee mark-up
From the 6 May briefing
The **TSJ Aragón** ruling on the Ecologistas en Acción challenge, the first European judicial test of a community data-centre case
From the 6 May briefing
Stargate UAE first-phase commissioning against the Q3 2026 target
From the 6 May briefing · Deadline: Q3 2026
GE Vernova Q2 backlog: any sign of demand revision, or a further extension of the 2030 slot stretch
From the 6 May briefing
Whether **Governor Janet Mills** signs, vetoes or lets the Maine moratorium lapse before the May 2026 decision window closes.
From the 26 Apr briefing · Deadline: May 2026
Whether **Ofgem** publishes its AI-demand consultation response this quarter, the document UK grid analysts treat as the most consequential of the year.
From the 26 Apr briefing
Whether **Synergy Research Group's** Q1 2026 hyperscale figures, due mid-May, confirm or break the $142 billion quarterly capex baseline.
From the 26 Apr briefing · Deadline: Q1 2026
Whether **EirGrid** and **ESB Networks** publish the CRU-mandated data centre connection process or formally explain its absence.
From the 26 Apr briefing
Whether **Stargate UAE** phase 1 commissions on its Q3 2026 schedule or joins the headline-to-ground gap.
From the 26 Apr briefing · Deadline: Q3 2026
Whether the **Tribunal Superior de Justicia de Aragón** admits the Ecologistas en Acción challenge for substantive hearing, setting a Spanish precedent.
From the 26 Apr briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.
- SignificantCorrected 1 Oct 2026We said
Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.
What was trueOn 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.
- SignificantCorrected 1 Oct 2026We said
Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.
What was trueOn 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.
- MinorCorrected 24 Sept 2026We said
Hill County, Texas is now defending against RCM Hill's $100 million claim
What was trueRCM Hill dismissed the case after Hill County dropped its ban (KWTX, 15 July 2026)
- SignificantCorrected 8 Sept 2026We said
Total contracted offers in the UK demand queue reached 125 GW by mid-2025, carried as an established queue total.
What was trueThe 125 GW cannot be reproduced from the register it is usually checked against. Lowdown counted NESO's Transmission Entry Capacity register on 8 September 2026: of 2,202 entries, 106 (4.8%) carry any demand component and none is demand alone, so the register cannot yield a demand-queue total. The figure traces to a NESO presentation attributing it to Energy Networks Association connection data, an image-only document we could not verify at source. NESO's own reformed connections pipeline reports 99 GW of transmission-connected demand.