The Record

Data Centres: Boom and Backlash

What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.

Happened 2 · Unresolved 1 · Open 75 · Corrections 132

What we told you to watch

Happened · 2

  • Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.

    From the 8 Sept briefing · Judged 22 Oct 2026

    SEA's Alto Jahuel case file is available and was checked.

  • Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.

    From the 8 Sept briefing · Judged 22 Oct 2026

    CRU approved MPID 345 on 22 September 2026.

Unresolved · 1

  • NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .

    From the 24 Sept briefing · Judged 22 Oct 2026

    Final ballot passed; Board adoption and FERC filing remain pending.

Still open · 75

Show the 10 most recent
  • Whether **Microsoft**, **Alphabet**, **Amazon** and **Meta** preserve their raised 2026 capex guidance through the late-July Q2 earnings cycle now that OpenAI's compute commitment has been visibly trimmed.

    From the 16 May briefing · Deadline: late-July

  • Whether **FERC** publishes the RM26-4-000 NOPR (Notice of Proposed Rulemaking) by end-June, and whether PJM's 18 May filing matches the language FERC accepted on 16 April.

    From the 16 May briefing · Deadline: 18 May

  • Whether the 18-21 May Denver, Seattle and Minneapolis votes produce a majority of refusals, consolidating the municipal moratorium tier into a default posture.

    From the 16 May briefing · Deadline: 21 May

  • Whether OpenAI's pivot to leased compute reroutes Q3 hyperscaler bookings toward **Equinix**, **Digital Realty** and other colocation operators, and whether Crusoe's Abilene inventory finds a second taker.

    From the 16 May briefing

  • The **FERC RM26-4-000** order at end of June: whether it constrains or accelerates large-load interconnection, and how it treats behind-the-meter cost allocation

    From the 6 May briefing · Deadline: end of June

  • Whether any second US state attempts a moratorium after the Maine veto, and whether the Sanders-Ocasio-Cortez federal proposal reaches a committee mark-up

    From the 6 May briefing

  • The **TSJ Aragón** ruling on the Ecologistas en Acción challenge, the first European judicial test of a community data-centre case

    From the 6 May briefing

  • Stargate UAE first-phase commissioning against the Q3 2026 target

    From the 6 May briefing · Deadline: Q3 2026

  • GE Vernova Q2 backlog: any sign of demand revision, or a further extension of the 2030 slot stretch

    From the 6 May briefing

  • Whether **Governor Janet Mills** signs, vetoes or lets the Maine moratorium lapse before the May 2026 decision window closes.

    From the 26 Apr briefing · Deadline: May 2026

  • Whether **Ofgem** publishes its AI-demand consultation response this quarter, the document UK grid analysts treat as the most consequential of the year.

    From the 26 Apr briefing

  • Whether **Synergy Research Group's** Q1 2026 hyperscale figures, due mid-May, confirm or break the $142 billion quarterly capex baseline.

    From the 26 Apr briefing · Deadline: Q1 2026

  • Whether **EirGrid** and **ESB Networks** publish the CRU-mandated data centre connection process or formally explain its absence.

    From the 26 Apr briefing

  • Whether **Stargate UAE** phase 1 commissions on its Q3 2026 schedule or joins the headline-to-ground gap.

    From the 26 Apr briefing · Deadline: Q3 2026

  • Whether the **Tribunal Superior de Justicia de Aragón** admits the Ecologistas en Acción challenge for substantive hearing, setting a Spanish precedent.

    From the 26 Apr briefing

What each side claimed

Claims are what a named side said at the time. We record them as said and judge them only against later evidence.

No claims recorded yet.

What we got wrong

Show the 10 most recent
  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta's El Paso data centre was described as running on, or having commissioned, a 366 MW behind-the-meter gas array, and as sitting inside ERCOT.

    What was true

    On 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan: El Paso Electric had applied to the Public Utility Commission of Texas and no ruling had issued. The plant was still unapproved on 1 October 2026 (ALJ recommendation 24 September 2026, no final order). El Paso Electric is in the Western Interconnection, not ERCOT.

    In xAI wins 41 gas turbines for Colossus

  • SignificantCorrected 1 Oct 2026
    We said

    Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.

    What was true

    On 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.

  • SignificantCorrected 1 Oct 2026
    We said

    Meta had commissioned a 366 MW behind-the-meter gas array at El Paso.

    What was true

    On 18 May 2026 El Paso Electric's application to the Public Utility Commission of Texas for the 366 MW McCloud gas plant serving Meta's El Paso data centre was pending, with no ruling. Administrative law judges recommended approval with conditions only on 24 September 2026, and no final order had issued by 1 October 2026.

    In DOE lets PJM switch off data centres

  • MinorCorrected 24 Sept 2026
    We said

    Hill County, Texas is now defending against RCM Hill's $100 million claim

    What was true

    RCM Hill dismissed the case after Hill County dropped its ban (KWTX, 15 July 2026)

    In Loudoun drafts a pause on data centres

  • SignificantCorrected 8 Sept 2026
    We said

    Total contracted offers in the UK demand queue reached 125 GW by mid-2025, carried as an established queue total.

    What was true

    The 125 GW cannot be reproduced from the register it is usually checked against. Lowdown counted NESO's Transmission Entry Capacity register on 8 September 2026: of 2,202 entries, 106 (4.8%) carry any demand component and none is demand alone, so the register cannot yield a demand-queue total. The figure traces to a NESO presentation attributing it to Energy Networks Association connection data, an image-only document we could not verify at source. NESO's own reformed connections pipeline reports 99 GW of transmission-connected demand.

    In UK queue: 50 GW DC vs 45 GW peak demand