Data Centres: Boom and Backlash

What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.

Happened 2 · Unresolved 1 · Open 75 · Corrections 132

What we told you to watch

Happened · 2

  • Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.

    From the 8 Sept briefing · Judged 22 Oct 2026

    SEA's Alto Jahuel case file is available and was checked.

  • Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.

    From the 8 Sept briefing · Judged 22 Oct 2026

    CRU approved MPID 345 on 22 September 2026.

Unresolved · 1

  • NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .

    From the 24 Sept briefing · Judged 22 Oct 2026

    Final ballot passed; Board adoption and FERC filing remain pending.

Still open · 75

Show the 10 most recent
  • Fingrid's submission of the revised KJV2026 (its grid code specifications for demand connections) to Finland's Energy Authority, ahead of a March 2027 confirmation target.

    From the 8 Sept briefing · Deadline: March 2027

  • Whether PUCT grants ERCOT's good-cause exception on 20 August, and whether a revised Batch Zero classification timetable is published alongside it

    From the 14 Aug briefing · Deadline: 20 August

  • Whether any load-serving entity, state commission or data-centre operator protests the IRAS terms in ER26-3380-000 before comments close at 5pm Eastern on 21 August

    From the 14 Aug briefing · Deadline: 21 August

  • Whether the DPEA holds its 8 September target decision now the Edinburgh appeal carries a full EIA

    From the 14 Aug briefing · Deadline: 8 September

  • Whether Nebius's next annual ICFR assessment reports the fixed-asset material weakness as remediated or carries it into 2027

    From the 14 Aug briefing

  • Whether PJM's Interim Resource Adequacy Service filing, due at FERC around 7 August, allows curtailment of large loads connecting after 1 June 2027 without dedicated supply, and how the large-load registry sequences them.

    From the 4 Aug briefing · Deadline: 7 August

  • What aggregate megawattage ERCOT's Batch Zero classification results show on 7 August, the first hard test of how much of the Texas queue is real rather than speculative.

    From the 4 Aug briefing · Deadline: 7 August

  • Whether developers respond to Ofgem's fee before the consultation closes on 16 September by withdrawing applications, which would shrink the 125 GW book without a single refusal being issued.

    From the 4 Aug briefing · Deadline: 16 September

  • Whether New Mexico's four sponsors pre-file their statewide moratorium bill ahead of the legislature reconvening in January 2027.

    From the 4 Aug briefing · Deadline: January 2027

  • Whether the six RTOs' 20 July generation-adequacy filings, still not public, show any grid able to serve its data-centre queue

    From the 25 Jul briefing · Deadline: 20 July

  • The Montgomery County, Maryland full council vote on 28 July

    From the 25 Jul briefing · Deadline: 28 July

  • Microsoft and Meta capex on 29 July and Amazon's on 30 July, testing whether Alphabet's raise is matched across the big four

    From the 25 Jul briefing · Deadline: 29 July

  • Whether New Mexico lawmakers table the promised statewide moratorium bill for the 2027 session

    From the 25 Jul briefing

  • Whether Hochul signs, vetoes or amends the Responsible Data Center Development Act before the year-end deadline, now that her executive order covers the same ground

    From the 15 Jul briefing

  • Whether the Indianapolis City-County Council ratifies the moratorium on 10 August or bends to Governor Braun's pro-investment stance

    From the 15 Jul briefing · Deadline: 10 August

  • Whether Q2 hyperscaler capex, reported after 20 July, accelerates against the tightening permit map or shows the first sign of siting caution

    From the 15 Jul briefing · Deadline: 20 July

  • Whether any developer challenges New York's executive order or Oregon's 29% tariff as a regulatory taking, the argument already filed against DOE curtailment

    From the 15 Jul briefing

  • Whether Hochul signs or vetoes New York's freeze, making it the first US statewide moratorium to take effect

    From the 7 Jul briefing

  • Whether Oregon's Public Utility Commission approves Portland General Electric's 29% large-load rate rise

    From the 7 Jul briefing

  • Whether another state copies Virginia's per-kilowatt-hour consumption tax now that one is enacted

    From the 7 Jul briefing

What each side claimed

Claims are what a named side said at the time. We record them as said and judge them only against later evidence.

No claims recorded yet.

What we got wrong

Show the 10 most recent
  • SignificantCorrected 22 Oct 2026
    We said

    Existing data centres in Seattle keep their current connections and can expand under pre-moratorium rules. Only new proposals above 20 MVA are blocked.

    What was true

    Existing data centres can keep operating. An expansion exemption permits at most another 20 MVA at eligible existing facilities; larger expansions also face the pause.

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    voted unanimously on 9 and 10 June to stop

    What was true

    voted unanimously on 9 June, with the mayor signing on 11 June, to stop

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    The ordinance exempts Seattle's existing data centres, which may keep expanding under current rules, so the freeze bites only on new arrivals.

    What was true

    Qualifying operating facilities can continue operating. Their expansion exemption is limited to an additional **20 MVA**, so larger expansions also fall under the moratorium.

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    making the freeze legally binding rather than provisional

    What was true

    with the ordinance taking effect when the mayor signed on **11 June**

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    voted **9 to 0** on **9 and 10 June** to enact

    What was true

    voted **9 to 0** on **9 June** to approve

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    voted 9 to 0 on 9 and 10 June to enact

    What was true

    voted 9 to 0 on 9 June to approve

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle's City Council voted 9-0 on 9 and 10 June. The vote made its 365-day moratorium legally binding on new loads above 20 MVA

    What was true

    Seattle's City Council approved its 365-day moratorium 9-0 on 9 June. It took effect with the mayor's signature on 11 June and applies to defined data centres above 20 MVA

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Existing data centres are exempt and may expand under current rules.

    What was true

    Operating facilities may continue, but the expansion exemption is limited to an additional 20 MVA; larger expansions are subject to the moratorium.

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle's City Council voted 9 to 0 on 9 and 10 June to enact the 365-day moratorium it had introduced on 30 April, making the freeze legally binding.

    What was true

    Seattle's City Council approved the proposed 365-day moratorium by 9 votes to 0 on 9 June. The ordinance took effect with the mayor's signature on 11 June.

    In Seattle locks in its data-centre freeze

  • MinorCorrected 22 Oct 2026
    We said

    The CRU decision text had not been checked.

    What was true

    CRU2026145 and CRU2026145c confirm the scope, date and derogation route.

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant data centres must seek a derogation.

    What was true

    The derogation route applies to transmission-connected data centres.

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant data centres must seek a derogation.

    What was true

    The derogation route applies to transmission-connected data centres.

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

  • MinorCorrected 22 Oct 2026
    We said

    The exact start date lacked primary confirmation.

    What was true

    CRU's approval letter confirms the effective date as 27 October 2026.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant sites must seek an exemption.

    What was true

    Only sites covered by MPID 345 need a derogation.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 applies to large electricity users generally.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All Irish data centres need an exemption if they cannot comply.

    What was true

    MPID 345 applies to transmission-connected data centres.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant data centres must seek an exemption.

    What was true

    The derogation route applies to transmission-connected data centres.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

    In CRU makes Irish sites ride through dips