The Record

Data Centres: Boom and Backlash

What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.

Happened 2 · Unresolved 1 · Open 75 · Corrections 132

What we told you to watch

Happened · 2

  • Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.

    From the 8 Sept briefing · Judged 22 Oct 2026

    SEA's Alto Jahuel case file is available and was checked.

  • Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.

    From the 8 Sept briefing · Judged 22 Oct 2026

    CRU approved MPID 345 on 22 September 2026.

Unresolved · 1

  • NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .

    From the 24 Sept briefing · Judged 22 Oct 2026

    Final ballot passed; Board adoption and FERC filing remain pending.

Still open · 75

Show the 10 most recent
  • Fingrid's submission of the revised KJV2026 (its grid code specifications for demand connections) to Finland's Energy Authority, ahead of a March 2027 confirmation target.

    From the 8 Sept briefing · Deadline: March 2027

  • Whether PUCT grants ERCOT's good-cause exception on 20 August, and whether a revised Batch Zero classification timetable is published alongside it

    From the 14 Aug briefing · Deadline: 20 August

  • Whether any load-serving entity, state commission or data-centre operator protests the IRAS terms in ER26-3380-000 before comments close at 5pm Eastern on 21 August

    From the 14 Aug briefing · Deadline: 21 August

  • Whether the DPEA holds its 8 September target decision now the Edinburgh appeal carries a full EIA

    From the 14 Aug briefing · Deadline: 8 September

  • Whether Nebius's next annual ICFR assessment reports the fixed-asset material weakness as remediated or carries it into 2027

    From the 14 Aug briefing

  • Whether PJM's Interim Resource Adequacy Service filing, due at FERC around 7 August, allows curtailment of large loads connecting after 1 June 2027 without dedicated supply, and how the large-load registry sequences them.

    From the 4 Aug briefing · Deadline: 7 August

  • What aggregate megawattage ERCOT's Batch Zero classification results show on 7 August, the first hard test of how much of the Texas queue is real rather than speculative.

    From the 4 Aug briefing · Deadline: 7 August

  • Whether developers respond to Ofgem's fee before the consultation closes on 16 September by withdrawing applications, which would shrink the 125 GW book without a single refusal being issued.

    From the 4 Aug briefing · Deadline: 16 September

  • Whether New Mexico's four sponsors pre-file their statewide moratorium bill ahead of the legislature reconvening in January 2027.

    From the 4 Aug briefing · Deadline: January 2027

  • Whether the six RTOs' 20 July generation-adequacy filings, still not public, show any grid able to serve its data-centre queue

    From the 25 Jul briefing · Deadline: 20 July

  • The Montgomery County, Maryland full council vote on 28 July

    From the 25 Jul briefing · Deadline: 28 July

  • Microsoft and Meta capex on 29 July and Amazon's on 30 July, testing whether Alphabet's raise is matched across the big four

    From the 25 Jul briefing · Deadline: 29 July

  • Whether New Mexico lawmakers table the promised statewide moratorium bill for the 2027 session

    From the 25 Jul briefing

  • Whether Hochul signs, vetoes or amends the Responsible Data Center Development Act before the year-end deadline, now that her executive order covers the same ground

    From the 15 Jul briefing

  • Whether the Indianapolis City-County Council ratifies the moratorium on 10 August or bends to Governor Braun's pro-investment stance

    From the 15 Jul briefing · Deadline: 10 August

  • Whether Q2 hyperscaler capex, reported after 20 July, accelerates against the tightening permit map or shows the first sign of siting caution

    From the 15 Jul briefing · Deadline: 20 July

  • Whether any developer challenges New York's executive order or Oregon's 29% tariff as a regulatory taking, the argument already filed against DOE curtailment

    From the 15 Jul briefing

  • Whether Hochul signs or vetoes New York's freeze, making it the first US statewide moratorium to take effect

    From the 7 Jul briefing

  • Whether Oregon's Public Utility Commission approves Portland General Electric's 29% large-load rate rise

    From the 7 Jul briefing

  • Whether another state copies Virginia's per-kilowatt-hour consumption tax now that one is enacted

    From the 7 Jul briefing

What each side claimed

Claims are what a named side said at the time. We record them as said and judge them only against later evidence.

No claims recorded yet.

What we got wrong

Show the 10 most recent
  • MinorCorrected 16 Nov 2026
    We said

    A Metropolitan Development Commission committee voted 10-3 on 13 July 2026 to recommend the moratorium.

    What was true

    The City-County Council's Metropolitan and Economic Development Committee cast the 10-3 vote (WFYI, 13/07/2026).

    In Indianapolis backs freezing new data centres

  • MinorCorrected 16 Nov 2026
    We said

    Red Eléctrica de España entity page: majority state-owned via SEPI

    What was true

    SEPI holds 20% of parent Redeia (Redeia shareholder page); entity 5364 background and two FAQ answers corrected via enrichment on 16/11/2026

  • SignificantCorrected 16 Nov 2026
    We said

    Charlotte entity page: Bank of America Stadium was a 2026 FIFA World Cup host venue

    What was true

    Charlotte was not one of the 11 US host cities for the 2026 World Cup; entity 7588 background, definition, search terms and quick facts corrected via enrichment on 16/11/2026

  • MinorCorrected 14 Nov 2026
    We said

    The regional leaders argued that the pause reflects OpenAI's US-first prioritisation rather than UK dysfunction.

    What was true

    The cited source gives their argument as the region keeping its AI Growth Zone status and being "open for business". The only analyst quoted, Professor Richard Whittle, called the pause a warning about the UK's AI-infrastructure model.

    In OpenAI pauses Cobalt Park Stargate site

  • MinorCorrected 14 Nov 2026
    We said

    North East Mayor Kim McGuinness and Nscale chief executive Bjoern Norda rejected the framing of the OpenAI pause.

    What was true

    The cited source (ResultSense via Prolific North, 23 April 2026) attributes the pushback to the North East Combined Authority, Dynamo North East and the North East Chamber of Commerce. It names neither McGuinness nor any Nscale executive. No person called Bjoern Norda can be found; Nscale's chief executive is Josh Payne.

    In OpenAI pauses Cobalt Park Stargate site

  • MinorCorrected 8 Nov 2026
    We said

    internal process notes published in the body

    What was true

    notes not for readers

  • MinorCorrected 8 Nov 2026
    We said

    internal process notes published in the body

    What was true

    notes not for readers

  • MinorCorrected 22 Oct 2026
    We said

    Amazon Web Services was the Amazon subsidiary that bought the former George Washington University site.

    What was true

    Amazon Data Services bought the site; AWS appears in the update through event 6435's historical comparison.

  • SignificantCorrected 22 Oct 2026
    We said

    Voted 9-0 on 9-10 June to enact a 365-day moratorium on new loads above 20 MVA

    What was true

    Approved a 365-day moratorium on defined data centres above 20 MVA by 9-0 on 9 June; the mayor signed on 11 June

    In Seattle locks in its data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Enacted the 365-day data-centre moratorium 9-0 on 9-10 June

    What was true

    Approved the 365-day data-centre moratorium 9-0 on 9 June; the mayor signed on 11 June

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle's 365-day freeze arrived five days after the Maine override failed

    What was true

    Seattle's proposed 365-day freeze followed the Maine override defeat

  • SignificantCorrected 22 Oct 2026
    We said

    when Seattle froze

    What was true

    when Seattle proposed its freeze

  • SignificantCorrected 22 Oct 2026
    We said

    and that process is now unavailable until at least **30 April 2027**.

    What was true

    but the April proposal had not yet enacted a year-long freeze.

    In Seattle proposes a year-long data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle's city council voted to pause new large data centre projects for one year

    What was true

    Seattle councilmembers proposed pausing new large data centre projects for one year

    In Seattle proposes a year-long data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle freezes data centres for a year

    What was true

    Seattle proposes a year-long data-centre freeze

    In Seattle proposes a year-long data-centre freeze

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle's moratorium exempts everything already connected.

    What was true

    Seattle's moratorium permits existing operations, but its expansion exemption is limited to an additional 20 MVA at eligible facilities.

  • SignificantCorrected 22 Oct 2026
    We said

    Seattle's City Council voted 9-0 on 9-10 June to make its 365-day moratorium legally binding on new loads above 20 MVA

    What was true

    Seattle's City Council approved its 365-day moratorium 9-0 on 9 June; it took effect with the mayor's signature on 11 June and covers defined data centres above 20 MVA

  • SignificantCorrected 22 Oct 2026
    We said

    The 9-0 ordinance exempts Seattle's existing data centres, which may keep expanding under current rules.

    What was true

    Existing facilities can keep operating, but the expansion exemption permits at most another **20 MVA** at eligible facilities.

  • SignificantCorrected 22 Oct 2026
    We said

    making the freeze binding rather than provisional

    What was true

    with the ordinance taking effect when the mayor signed on **11 June**

  • SignificantCorrected 22 Oct 2026
    We said

    voted **9 to 0** on **9 and 10 June** to enact

    What was true

    voted **9 to 0** on **9 June** to approve