Data Centres: Boom and Backlash
18OCT

Johor halts data-centre approvals after water protest

2 min read
13:11UTC

Johor stopped approving Tier 1 and Tier 2 data centres after Malaysia's first water-rights protest at a facility; SCMP reports applicants are being told to wait for water connections until mid-2027.

IndustryDeveloping
Key takeaway

Johor's halt imports a UN human-rights framework into South East Asian data-centre regulation.

Johor, the Malaysian state hosting most of the country's data-centre investment, halted approvals for Tier 1 and Tier 2 facilities in late April 2026 after the country's first water-rights protest at a data-centre facility. The Diplomat reported the halt on 27 April, framing the underlying community challenge under the UN Guiding Principles on Business and Human Rights. SCMP reported that applicants are being told to wait for water connections until mid-2027, an effective 14-month freeze for any project not already in the pipeline.

The Diplomat's invocation of the UN framework sits at the centre of the structural change. The UN Guiding Principles on Business and Human Rights, adopted by the UN Human Rights Council in 2011, set a corporate responsibility to respect human rights including the right to water under General Comment 15. The Diplomat's invocation of the framework places Johor's halt in the same legal-conceptual category as the Milwaukee Riverkeeper action against Microsoft's Mount Pleasant campus in Wisconsin, where a water-disclosure non-disclosure clause was broken by litigation. The framework does not mandate a particular regulatory outcome; it changes the disclosure obligations and the legal vocabulary available to communities challenging individual sites.

Johor matters because of where it sits in the Asia-Pacific compute map. The state hosts data-centre investment from AirTrunk, Equinix, Bridge Data Centres, GDS, and several Singaporean and Chinese hyperscalers, drawn across the causeway by Singapore's own moratorium and by Johor's lower power costs. A 14-month water-connection freeze rebalances site selection toward Indonesia (Batam, Bintan), the Philippines, and Vietnam, all of which carry their own water-stress and grid-stability constraints. The halt is unlikely to produce a permanent freeze, given the economic-development pressure inside the Malaysian state government, but the precedent of a UN-framework community challenge surviving long enough to alter approvals is the new regional baseline.

Deep Analysis

In plain English

Johor is a Malaysian state just across the Johor Strait from Singapore. It has become popular with data centre companies because electricity is cheap and it sits next to Singapore's major internet infrastructure. Data centres use large amounts of water for cooling, especially in a hot and humid climate like Malaysia's, where the cooling systems run harder than in cooler countries. A local community held the country's first protest specifically about data centre water use, and authorities responded by pausing new data centre approvals until mid-2027, affecting both major (Tier 1) and medium-sized (Tier 2) projects. A policy journal, The Diplomat, reported the case as a human-rights issue about who has the right to access clean water when industrial users compete with local communities.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

The Diplomat· 6 May 2026
Read original →
Different Perspectives
Nexus Core Systems
Nexus Core Systems
Hired FiveNines Group, in a deal announced on 8 October, for early design, feasibility and permit work on a 20 MW AI data centre near Casablanca. It is the first named site of a planned 180 MW programme, still at concept design.
MC Digital Realty
MC Digital Realty
Began building the 24 MW KIX15 data centre in Osaka Prefecture on 7 October, due to open in the fourth quarter of 2028. The joint venture of Digital Realty and Mitsubishi Corporation says it will then run 10 data centres in Japan with about 220 MW of IT capacity.
KT Cloud
KT Cloud
Said on 7 October that it and Hyundai Engineering will build a 50 MW AI data centre at Cheongna, Incheon, from the fourth quarter of 2026. Completion is due in the first quarter of 2030, part of KT Cloud's target of more than 1 GW of AI capacity by 2031.
Town of Trebbin
Town of Trebbin
Said on 7 October that work has begun on two data-centre buildings and a substation under building permits already granted. The operating permit under the Federal Immission Control Act is still with Brandenburg's environment agency, so the town postponed its public presentation.
Óscar López, Digital Transformation minister
Óscar López, Digital Transformation minister
Said in Madrid on 8 October that he hopes to approve the data-centre royal decree shortly, with urgent processing to reach the cabinet before the 29 November election. He said the final text will take the more than 600 submissions into account, without saying what changes.
Hydro-Québec
Hydro-Québec
Defended its proposed Tarif CD before the Régie de l'énergie du Québec from 1 to 9 October, a rate for data centres of 5 MW or more that adds a premium when peak demand stays below 60% of forecast. Industrial consumers filed their own wording for the clause on who the rate covers.