Data Centres: Boom and Backlash
8SEP

Indiana counties turn pauses into bans

1 min read
13:06UTC

Marshall and Cass counties banned new data centres outright, with no end date, part of roughly 30 of Indiana's 92 counties now restricting a build-out they once merely paused.

IndustryDeveloping
Key takeaway

Two Indiana counties replaced temporary pauses with permanent data-centre bans, removing the reopening date moratoria always kept.

Marshall and Cass counties in Indiana have banned new data centres outright rather than pausing them, part of roughly 30 of the state's 92 counties now restricting development. 1 A moratorium sets a clock; a ban does not. That distinction marks the shift, because it removes the reopening date every earlier Indiana pause carried.

The move escalates a county-by-county trend the beat has counted for months. In June, Boone County became Indiana's twelfth to pass a one-year moratorium ; Marshall and Cass set no end date at all. Roughly a third of the state's counties now sit somewhere on the spectrum from pause to prohibition.

The bans do not touch the demand. Governor Mike Braun is still selling Indiana to hyperscalers, a state-level pitch that runs directly against the counties now shutting them out. That split, a governor recruiting the load while local boards refuse it, is the shape the Indiana fight has settled into.

Deep Analysis

In plain English

Two more Indiana counties, Marshall and Cass, have gone further than most: instead of pausing new data centres for a year or two while they write rules, they have banned them outright, with no plan to revisit the decision. Around a third of Indiana's 92 counties now restrict data centres in some way. No governor or state law forced this decision. Each of Indiana's 92 counties is deciding on its own, so the state's data-centre map is becoming a patchwork of banned, paused and open areas rather than one statewide policy.

Deep Analysis
Root Causes

Marshall and Cass counties chose outright bans rather than the moratoria most of Indiana's other restricting counties adopted because a moratorium requires the county to eventually write zoning rules that let some future project through; a ban carries no such obligation and needs no follow-up ordinance, making it the structurally simpler tool for a county with no active project to actually manage.

Indiana's fragmented pattern, roughly a third of its 92 counties now restricting development with no state law or governor's action behind any of it, exists because Indiana zoning authority sits almost entirely at the county level. Unlike New York's single executive order, no one Indianapolis decision can freeze the state, so each county reaches its own answer at its own pace.

What could happen next?
  • Consequence

    Developers face a state where roughly a third of counties are permanently closed rather than temporarily paused, narrowing the map for new Indiana campuses.

First Reported In

Update #10 · New York freezes data centres by decree

WFYI· 15 Jul 2026
Read original
Causes and effects
This Event
Indiana counties turn pauses into bans
Indiana's data-centre backlash has hardened from temporary moratoria into permanent bans across a third of its counties.
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.