Data Centres: Boom and Backlash
8SEP

Amazon's $137.2bn of leases it hasn't opened

2 min read
13:06UTC

Amazon's 10-Q for the June quarter discloses $137.2bn of leases not yet commenced, a number more than 60 per cent larger than the capex guidance figure the market actually tracks.

IndustryDeveloping
Key takeaway

Amazon has signed $137.2bn of data-centre leases on buildings that have not yet been delivered.

Amazon filed its Form 10-Q for the quarter ended 30 June with the US Securities and Exchange Commission on Friday 31 July, disclosing $650.0bn of total contractual commitments⁠1. One line inside that table appeared in no earnings-call commentary: $137.2bn of leases not yet commenced, meaning buildings Amazon has signed for where the facility has not yet been delivered, overwhelmingly data-centre and power infrastructure. Unconditional purchase obligations, which the filing says include long-term energy procurement, add a further $130.1bn⁠2.

Cash capital expenditure, the money actually spent on physical assets in the period, ran to $53.1bn in the quarter against $31.4bn a year earlier, a rise of 69 per cent, and $96.3bn across the first half⁠3. Amazon raised full-year 2026 guidance to roughly $220bn, citing memory costs and continued cloud investment. That figure counts only the cash it expects to lay out this year.

Guidance and the lease line measure different things, and the gap between them is where the planning problem sits. A lease not yet commenced is a building somewhere that a landlord is contracted to deliver and Amazon is contracted to take, with a grid connection behind it that some system operator has to find. None of that shows up in the number quoted when a campus goes before a planning committee.

Virginia's regulator issued Amazon's Lake Anna cooling-water discharge permit on 21 July, assessed as one campus drawing on one river. The pipeline sitting in the 10-Q is a portfolio-scale commitment being permitted one site at a time, by bodies that see only the site in front of them.

Deep Analysis

In plain English

When a company files its quarterly results with US financial regulators, it has to list what it spent this year and, separately, what it has already promised to spend in future, even on buildings that are not finished yet. Amazon's filing shows it has signed $137.2bn worth of data-centre leases for facilities that have not opened, which is more money than its entire announced budget for building data centres this year. That gap matters because most headlines about Amazon's spending only report the smaller, current-year figure.

Deep Analysis
Root Causes

The structural cause is that data-centre leasing separates the signing of a long-term contract from the physical delivery of the building, unlike direct capital expenditure which Amazon records as spending occurs. A hyperscaler can lock in years of future capacity with a lease commitment long before construction finishes, which lets its balance sheet carry contracted growth that its published capex guidance, a cash-flow figure for the current year only, does not capture.

A second structural driver is Amazon's own disclosure that unconditional purchase obligations, including long-term energy procurement agreements, total $130.1bn, reflecting that securing future power supply now requires the same kind of multi-year contractual commitment as securing the buildings themselves.

What could happen next?
  • Meaning

    Headline hyperscaler capex guidance understates the true scale of contracted future data-centre capacity by tens of billions of dollars.

  • Consequence

    Communities and regulators debating local moratoria may be assessing a materially smaller pipeline than the one Amazon has already committed to build.

First Reported In

Update #12 · Ofgem prices the grid queue by the megawatt

US Securities and Exchange Commission· 4 Aug 2026
Read original →
Causes and effects
This Event
Amazon's $137.2bn of leases it hasn't opened
The commitment Amazon has already contracted for sits in a filing table rather than in guidance, so the counties weighing individual campuses work from the smaller number.
Different Perspectives
Mohsen Rezaei
Mohsen Rezaei
The senior Iranian security official and former IRGC commander told Press TV that US-linked technology infrastructure in the region could become a target if war resumes. He named the UAE and valued the assets at more than US$2 trillion, without a breakdown.
Mykhailo Shelemba
Mykhailo Shelemba
Datagroup's chief executive says the Kyiv data centre hit on the night of 18 to 19 October is beyond repair. Services continue from backup sites, and no staff were hurt.
Kristen Umstattd
Kristen Umstattd
The Loudoun supervisor voted against fast-tracking Amazon's rezoning of the Ashburn campus. She said there were no figures yet on homes, school or road costs.
Akishima residents' litigation group
Akishima residents' litigation group
The group formed on 18 October and plans to sue Nihon GLP by year-end to stop eight data-centre buildings. Its lawyers will argue rights to life, health, clean water and a natural environment after mediation failed in August.
Óscar López
Óscar López
Spain's Digital Transformation minister said on 22 October he could not confirm when the data-centre decree will be approved. He added that Google has always committed to investing in Spain.
Google
Google
Google said it would comply with LVV's order to stop preparatory works at Muhos and Kajaani until environmental assessments finish. A spokesperson conceded the company had fallen short.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.