Data Centres: Boom and Backlash
15JUL

New York freeze waits on Hochul

2 min read
13:16UTC

New York's data-centre permit freeze cleared both chambers on 4 June and now sits unsigned on Governor Kathy Hochul's desk; a North Country lawmaker urged a veto on 30 June.

IndustryDeveloping
Key takeaway

New York's statewide freeze needs only a signature, but the backlash is already spreading below the statehouse.

New York's Responsible Data Center Development Act passed the Assembly 102-39 and the Senate 44-16 on 4 June and now waits on a single signature.⁠1 The bill imposes a one-year hold on new permits from the state Department of Environmental Conservation (DEC) for any data centre of 20 MW or more, with projects already under construction exempt.

It does more than pause building. The Act carves data centres into a separate large-load utility class so their grid-reinforcement costs cannot be spread onto household bills, orders an 18-month environmental impact study framework, and sets renewable-sourcing targets rising to one-third by 2030. Governor Kathy Hochul has neither signed nor vetoed it. She says she wants communities with pending projects to secure the best terms first, while a North Country lawmaker publicly urged a veto on 30 June.⁠2 If she signs, it becomes the first US statewide freeze to actually take effect, after Maine's version fell to a governor's veto in April.

Seattle enacted its own 365-day freeze in June, and Indiana counties are now restricting data centres one board at a time. That is why New York's outcome, whichever way Hochul rules, no longer decides the direction of the backlash on its own.

Deep Analysis

In plain English

New York's legislature passed a bill weeks ago that would pause new data-centre permits for a year, but it only becomes law if Governor Hochul signs it, and she has not said yet. If she does, the freeze would only apply to new data centres of 20 megawatts or larger, roughly enough power for tens of thousands of homes; anything already under construction keeps going. Meanwhile at least one lawmaker in the state's north has publicly asked her to veto it instead.

Deep Analysis
Root Causes

New York's environmental review process has no load-based trigger: a data centre is permitted under the same criteria as any industrial building, regardless of whether it draws 2 MW or 200 MW. The Responsible Data Center Development Act's substantive change is inserting a threshold, 20 MW, into a review framework that previously treated electricity demand as invisible to planners.

The bill also answers a data gap regulators have struggled with. New York, unlike Texas's ERCOT interconnection queue, has no public grid-level accounting of pending large loads, so the state has been assessing impact site by site rather than system-wide.

What could happen next?
  • Consequence

    A Hochul signature would make New York the first US state to enact a data-centre moratorium since Maine's veto, reviving a model other legislatures had treated as dead.

  • Opportunity

    Exempting projects already under construction lets developers who broke ground before the freeze keep building while newer applicants face the pause.

First Reported In

Update #9 · US data-centre backlash becomes law

DLA Piper· 7 Jul 2026
Read original →
Causes and effects
This Event
New York freeze waits on Hochul
Hochul's signature would make New York the first US statewide moratorium to take effect, reviving a model Maine's veto was thought to have buried.
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.