Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
26APR

IEA: 17% growth, $700B capex run-rate

3 min read
09:44UTC

The IEA's 16 April release put global data centre electricity demand growth at 17% in 2025, six times the overall electricity growth rate, with five hyperscalers' capex topping $400 billion and projected to reach roughly $700 billion in 2026.

IndustryDeveloping
Key takeaway

Capex topped $400B in 2025 and is forecast at $700B in 2026; the binding constraint is no longer capital.

The International Energy Agency (IEA) released its updated data centre electricity report on 16 April 2026, restating the growth curve in maximalist terms. 1 Global data centre electricity demand grew 17% in 2025, six times the 3% overall global electricity growth rate, with AI-focused facilities expanding by roughly 50%. Five major tech companies collectively topped $400 billion in capex in 2025, a figure the IEA expects to rise a further 75% in 2026 to about $700 billion. 2

The IEA is the OECD's energy modelling agency in Paris, the body whose annual World Energy Outlook sets the baseline most utilities and finance ministries use for grid planning. When it puts a number on hyperscaler capex, the figure is sourced directly from company filings and disclosed corporate energy data, not industry analyst projections. The 2025 total absorbed roughly 485 TWh of global electricity at data centres alone.

Conditional agreements for small modular reactor (SMR) power for data centres jumped from 25 GW at end-2024 to 45 GW by April, a near-doubling of paper nuclear in sixteen months. 3 No commercial SMR has yet powered a data centre anywhere in the world; the GW figures are letters of intent, not interconnection agreements. The pipeline reflects what hyperscalers want to procure, not what the supply chain can deliver this decade.

Capex and chips have stopped binding the build-out. Credit lines remain open at unprecedented scale and the silicon supply has caught up enough to absorb the dollars. What stops a project in April 2026 is grid headroom, planning approval, water permits, and increasingly state legislatures, not capital. The five sections that follow trace what happens when a $700 billion spend curve meets jurisdictions that are starting to refuse the load.

Deep Analysis

In plain English

A data centre is a large building full of computers that run cloud storage, streaming, and AI services. Every computation uses electricity and generates heat. As AI models have grown larger and more complex, the computers running them need far more power per square metre of floor space than earlier generations. The IEA is the International Energy Agency, a Paris-based international body that tracks global energy use. Its 16 April figures show that data centres worldwide used 485 TWh of electricity in 2025, about the same as the entire United Kingdom. That is up 17% from the year before, while total global electricity use grew only 3%. SMRs, or small modular reactors, are a type of nuclear power station being developed at smaller scale than traditional plants. Tech companies are signing agreements to buy electricity from SMRs that have not been built yet, because they do not expect the ordinary electricity grid to have enough spare capacity to meet their needs.

Deep Analysis
Root Causes

Data centre electricity demand is growing at a multiple of overall grid growth because AI inference workloads are power-dense in ways general-purpose computing is not. A 2027-era AI server rack draws power equivalent to roughly 65 UK households; a 2020-era rack drew the equivalent of about six. This is not a scheduling or efficiency problem, it is a physics constraint on the rate at which waste heat can be removed and power delivered.

The SMR pipeline jump from 25 to 45 GW in 16 months reflects a secondary cause: grid operators in the UK, US, and EU cannot connect new load at the pace operators require, so operators are contracting alternative generation sources. SMR agreements are conditional and multi-decade; they signal intent, not delivered capacity.

What could happen next?
  • Consequence

    At the IEA's central 2030 projection, data centres would consume approximately 950 TWh globally, equivalent to adding Japan's entire electricity demand to the sector in five years.

    Medium term · Medium
  • Risk

    SMR conditional agreements at 45 GW represent procurement intent, not delivered capacity; if nuclear licensing timelines hold to historical rates, most will not commission before 2035.

    Long term · High
  • Opportunity

    Countries with surplus low-carbon generation capacity and permissive planning frameworks, Iceland, Norway, parts of Canada, stand to attract disproportionate hyperscaler investment as consent constraints tighten elsewhere.

    Medium term · Medium
First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

International Energy Agency· 26 Apr 2026
Read original
Different Perspectives
Johor state authority and Malaysian community
Johor state authority and Malaysian community
Johor halted Tier 1 and Tier 2 approvals after Malaysia's first water-rights protest; applicants face a mid-2027 floor on connections. The Diplomat's framing under UN Guiding Principles on Business and Human Rights imports a disclosure regime that ASEAN regulators had not previously applied to data-centre water consumption.
G42 and UAE sovereign programme
G42 and UAE sovereign programme
G42 confirmed all long-lead equipment procured for the 200 MW Stargate UAE first phase targeting Q3 2026; sovereign demand pull from the UAE government as anchor tenant provides cost patience commercial capital cannot replicate despite year-round mechanical cooling raising PUE to 1.35-1.50.
OpenAI and UK government
OpenAI and UK government
OpenAI cited UK industrial electricity at 'more than four times' US and Nordic rates as a co-equal Cobalt Park barrier alongside NESO's 50 GW grid queue. The named multiplier drops the UK off the global top-10 for new greenfield builds independent of any queue reform NESO can deliver in the near term.
Ecologistas en Acción and community challengers
Ecologistas en Acción and community challengers
Ecologistas en Acción's TSJ Aragón challenge to Amazon's 30-building expansion produced no ruling in the window, leaving Aragón's third-place global ranking under judicial cloud. The Virginia Court of Appeals precedent on inadequate public notice gives European community groups a template to apply to Spanish regional planning law.
FERC and US state regulators (NESO, EirGrid)
FERC and US state regulators (NESO, EirGrid)
FERC pledged on 16 April to act by end of June on RM26-4-000, the first federal rulebook for loads above 20 MW. Ireland's CRU on-site-generation rule, now templated by Pure DC's 110 MW Dublin microgrid, shows that a freeze paired with a defined compliance route can reopen a closed market.
Hyperscaler operators (Microsoft, Alphabet, Amazon, Meta)
Hyperscaler operators (Microsoft, Alphabet, Amazon, Meta)
All four reported Q1 2026 earnings with no downward revision to combined 2026 capex of $725 billion, treating the moratorium wave as a routing problem rather than a demand signal. Microsoft's $37 billion AI annual run rate confirms that capital allocation runs on quarterly board cycles that five-to-eight-year consent timelines cannot disrupt.