Equinor's Troll West Increased Gas Recovery North subsea project, FID'd 19 June 2026, targeting 11 bcm of additional recoverable gas with first production in 2028.

Last refreshed: 22 June 2026 · Appears in 1 active topic

Key Question

Does TWIN add any gas before winter 2026, or is it purely a 2028 commitment?

Timeline for TWIN

#20 19 Jun

Equinor takes FID on Troll TWIN

European Energy Markets
View full timeline →

Background

Equinor and its Troll licence partners took final investment decision on TWIN (Troll West Increased Gas Recovery North) on 19 June 2026, committing NOK 4 billion to unlock an estimated 11 billion cubic metres of additional recoverable gas. First production is targeted for 2028. The project landed one week after the EU's short-term ban on remaining Russian pipeline gas volumes came into force, reinforcing Norwegian supply as the structural answer to European import diversification.

TWIN is a brownfield subsea tieback to existing Troll A infrastructure on the Norwegian Continental Shelf, operated by Equinor with partners Petoro (55.93%), Shell (8.19%), TotalEnergies (3.69%), and ConocoPhillips (1.64%). The Troll field has been in production since 1996 and already supplies roughly 11% of Europe's gas imports; TWIN extends its productive life and partially offsets natural decline in the western part of the reservoir.

For European gas markets, TWIN is a 2028-horizon commitment with no effect on the current injection season or winter 2026/27 storage builds. Its significance is structural: it anchors Norwegian shelf investment at a point when European buyers are locking in long-term supply contracts outside Russian dependency, and it demonstrates continued commercial confidence in Norwegian Continental Shelf development despite an uncertain forward price curve.

Common Questions
What is the Troll TWIN project and when will it produce gas?
TWIN (Troll West Increased Gas Recovery North) is a NOK 4 billion subsea tieback on Norway's Troll field that received final investment decision in June 2026. It targets 11 bcm of additional gas with first production in 2028.Source: Equinor/Lowdown
Who are the partners in the Troll TWIN project?
Partners are Equinor (operator), Petoro (55.93%), Shell (8.19%), TotalEnergies (3.69%), and ConocoPhillips (1.64%).Source: Equinor
Does the TWIN project help Europe replace Russian gas?
Not immediately. TWIN first production is targeted for 2028, so it offers no relief for the current injection season or winter 2026/27. It is a structural supply commitment, not an emergency response.Source: Lowdown analysis
How much gas does the Troll field already supply to Europe?
The Troll field supplies roughly 11% of Europe's gas imports. TWIN is a brownfield extension that partially offsets natural decline in the Troll West reservoir.Source: Equinor