Project Jupiter
Nation / PlaceUS

Project Jupiter

Oracle/OpenAI hyperscale data-centre campus under construction at Santa Teresa, New Mexico.

Last refreshed: 25 July 2026 · Appears in 1 active topic

Key Question

Can Project Jupiter run without the gas pipeline New Mexico just blocked twice?

Timeline for Project Jupiter

#11 21 Jul
#11 15 Jul

Continued construction despite losing its planned behind-the-meter power source

Data Centres: Boom and Backlash: New Mexico vetoes Jupiter gas pipeline
View full timeline →

Background

Project Jupiter is a hyperscale AI data-centre campus that Oracle and OpenAI are building at Santa Teresa in Doña Ana County, part of the wider Stargate build-out. Construction, which began in September 2025, kept advancing through July even as New Mexico's Land Commissioner rejected the gas pipeline meant to power it for a second time.

At roughly 1,400 acres, big enough to swallow New York's Central Park, the campus is designed to draw up to 2.5 gigawatts, more than half of New Mexico's total generating capacity, from a behind-the-meter microgrid rather than the public grid. Oracle and OpenAI's development partners, BorderPlex Digital Assets and Stack Infrastructure, are targeting initial operations in the fourth quarter of 2026; by spring the site already had over 1,200 construction workers.

Jupiter's split between granted land-use consent and blocked fuel supply has become a template for how US states are separating data-centre approval from power approval. Its progress, or lack of it, is a bellwether for the wider Stargate programme's ability to actually energise the capacity it has announced.

Common Questions
What is Project Jupiter in New Mexico?
Project Jupiter is an Oracle and OpenAI hyperscale data-centre campus under construction at Santa Teresa, New Mexico, part of the Stargate AI infrastructure programme.Source: background
Why was Project Jupiter's power supply blocked?
New Mexico's State Land Commissioner twice rejected the Green Chili gas pipeline lateral that would have fed Jupiter's behind-the-meter microgrid, citing emissions against trust revenue.Source: background
How much power does Project Jupiter need?
Up to 2.5 gigawatts, more than half of New Mexico's entire generating capacity, drawn from an onsite microgrid rather than the public grid.Source: background
When will Project Jupiter start operating?
Developers are targeting initial operations in the fourth quarter of 2026, though construction began in September 2025.Source: background