
Energinet
Danish state-owned operator of the country's electricity and gas transmission systems.
Energinet ended its temporary large-load connection pause in June 2026 and replaced the former rolling process with pooled assessment and stricter maturity criteria for larger projects.
Last refreshed: 22 October 2026 · Appears in 2 active topics
Will pooled grid assessments unblock Denmark's queued large-load projects?
Timeline for Energinet
Mentioned in: Jemena halts power line to NEXTDC's M3
Data Centres: Boom and BacklashMentioned in: Irish regulators split over data centres
Data Centres: Boom and BacklashExtended the pause on new large-load connection agreements, citing a 60 GW queue against 7 GW peak demand
Data Centres: Boom and Backlash: Denmark halts its clean wind-grid queueBackground
Energinet is Denmark's state-owned electricity and gas transmission system operator. It manages the high-voltage networks that carry energy across Denmark and connect the country with neighbouring systems. For large electricity users, its connection process determines whether a project can obtain transmission capacity and on what timetable.
Denmark's large-load queue showed why abundant renewable generation does not by itself guarantee a connection. In May 2026, Energinet reported a 60 GW queue against national peak demand of roughly 7 GW. The temporary pause has since ended. Pooled assessment now lets Energinet rank larger requests by project maturity and priority against the capacity it expects to make available.
Energinet replaces the temporary pause
Energinet's three-month pause on new large connection agreements ended in June 2026. Larger requests did not return to the former rolling process. They moved into pooled assessment with maturity and prioritisation criteria, allowing the operator to compare projects against limited capacity.
The pause followed a queue of 60 GW against Danish peak demand of about 7 GW. Energinet moved from a blanket temporary stop to selective allocation rather than reopening unrestricted access. Larger projects now compete on their readiness and priority as well as the network capacity available to serve them.
Why did Energinet pause new large grid connections?
Is Denmark still a good location for data centres?
Which European countries have paused data centre grid connections?
How big is Denmark's data centre electricity queue compared to its grid?
How does Energinet now assess large connection requests?
Is Energinet's 2026 grid connection pause still in force?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 22 October 2026. Editorial standards.