Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
DOE Organisation Act
AI-generated illustration
LegislationUS

DOE Organisation Act

1977 US law creating the Department of Energy; Section 403 authorises the Secretary to direct FERC rulemaking.

As of November 2026, the large-load rulemaking that Energy Secretary Chris Wright opened under the act's Section 403 has drawn plans from six grid operators, filed between 13 and 20 November, none yet accepted by FERC.

Last refreshed: 26 November 2026 · Appears in 1 active topic

Key Question

How does a 1977 energy law end up shaping where data centres can connect to the US grid?

Timeline for DOE Organisation Act

#19 20 Nov
#2 16 Apr

FERC commits to June 2026 grid-load order

Data Centres: Boom and Backlash
View full timeline →

Background

The Department of Energy Organization Act was signed on 4 August 1977 as Public Law 95-91. It created the US Department of Energy and set up the Federal Energy Regulatory Commission inside it as an Independent commission, so the department and the regulator share a statute but not a chain of command.

Section 403 is the clause that links them. It lets the Energy Secretary propose rules on matters within FERC's remit and set reasonable deadlines for a decision. FERC keeps exclusive jurisdiction over any such proposal and must consider it and take final action, which is a duty to decide rather than a duty to agree.

That clause is the legal root of docket RM26-4-000, the federal attempt to standardise how loads above 20 MW, chiefly data centres, join the interstate grid. Every grid-operator filing in that proceeding, including the November 2026 non-firm service plans, traces back to a Section 403 letter.

Key Issues
Large-load rulemaking

Section 403 set FERC's data-centre agenda

Wright invoked Section 403 on 23 October 2025 to direct FERC to write rules for connecting electricity loads above 20 MW, which in practice means data centres. The docket is RM26-4-000, and on 16 April 2026 FERC promised to act on it by the end of June.

The statute let the Secretary choose the subject but left the answer to the Commission, and FERC picked a slower route: show-cause orders to its six regulated grid operators on 18 June. Their replies landed between 13 and 20 November 2026. Each offers cheaper power that can be interrupted, and four put a price on the trigger, from $25 to $250 per megawatt-hour. As of 20 November FERC had approved none of them.

Common Questions
What is Section 403 of the DOE Organisation Act?
It lets the Energy Secretary propose rules on matters FERC regulates, and requires FERC to consider and take final action on them within reasonable time limits the Secretary sets. Chris Wright used it on 23 October 2025 to start FERC's large-load rulemaking.Source: 42 U.S.C. 7173
When was the Department of Energy Organisation Act passed and what does it do?
It was enacted on 4 August 1977 as Public Law 95-91. It created the Department of Energy and set up FERC within it as an Independent commission; Section 403 lets the Secretary put rule proposals to FERC.Source: Public Law 95-91
How often does the Energy Secretary invoke Section 403 against FERC?
Section 403 directions to FERC are rare. The Trump administration's use of it for RM26-4-000 in October 2025 is read by energy-law practitioners as a deliberate signal that AI data-centre infrastructure is an administration priority, rather than a routine energy-security matter.Source: Mayer Brown
What is FERC Docket RM26-4-000 about?
RM26-4-000 is the FERC rulemaking on how electricity loads above 20 MW, chiefly AI data centres, connect to the interstate grid. Energy Secretary Chris Wright opened it in October 2025 under Section 403. FERC answered in June 2026 with show-cause orders to the six grid operators rather than a final rule.Source: FERC
Did FERC meet the Energy Secretary's 30 April 2026 deadline for data-centre grid rules?
No. Wright's Section 403 letter asked for final action by 30 April 2026. FERC said on 16 April it would act by the end of June, then issued show-cause orders on 18 June instead of a final rule.Source: Department of Energy
Source Material

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.