Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Artemis II
EventUS

Artemis II

Completed April 2026 crewed lunar flyby; first humans beyond LEO since Apollo 17.

Last refreshed: 17 April 2026 · Appears in 1 active topic

Key Question

Why has NASA withheld crew radiation data after three public windows?

Timeline for Artemis II

View full timeline →
Common Questions
What happened to Artemis II after splashdown?
The crew splashed down on 10 April 2026 and held a press conference on 16 April. Three technical questions remain open: helium leak 10x predictions, heat shield scan pending, and radiation data unreleased.Source: Lowdown / NASA
Why hasn't NASA released Artemis II radiation data?
NASA states crew dose data follows peer-review publication timelines rather than press release timelines. Three scheduled public windows passed without disclosure as of 16 April.Source: NASA / Lowdown
Was the Artemis II heat shield OK?
The administrator gave a preliminary visual clearance on 13 April, but the formal 30-day inspection at KSC had not started at the crew conference. Wiseman said he saw 'a little loss of charred material on the shoulder'.Source: Associated Press / NASA
How much did Artemis II cost?
Each SLS/Orion flight costs approximately $4 billion, against a programme total exceeding $93 billion since 2012, per the NASA OIG.Source: NASA OIG

Background

Artemis II launched on 1 April 2026 and splashed down in the Pacific on 10 April, completing the first crewed mission beyond low Earth orbit in more than fifty years. The crew of Reid Wiseman, Victor Glover, Christina Koch, and Jeremy Hansen flew Orion on a ten-day lunar flyby, passing within roughly 8,900 km of the Moon before a lofted re-entry designed to reduce heat-shield peak loading. Six days after splashdown the crew gave a post-flight press conference at Johnson Space Center, at which Commander Wiseman praised the heat shield as looking "wonderful" and pledged a "fine-tooth comb" inspection of every atom.

Three post-mission technical questions remain open. The O2 manifold helium leak operated at 10 times the rate ground tests predicted; a redesigned valve is non-negotiable for Artemis IV lunar-orbit operations where blowdown mode is not available. The heat shield received an immediate visual clearance from Isaacman on 13 April but the formal 30-day KSC scan had not yet begun at the time of the crew conference. Crew radiation dose data from a mission that absorbed a G3 geomagnetic storm and an M7.5 solar flare has not been released after three scheduled public windows.

The mission cost approximately $4 billion against a $93 billion programme total, making each open engineering question a public accountability issue as much as a technical one. Artemis II's completion activates the Artemis III stack: the SLS core stage leaves Michoud Assembly Facility on 20 April, while the Orion capsule and ESM-3 are already at KSC inside the Armstrong Operations and Checkout Building. China's crewed lunar target of 2030 remains the schedule pressure against which every unresolved anomaly is measured.