Germany's network regulator, the Bundesnetzagentur, ran the first auction under StromVKG, the law that pays firms to build plants for scarce hours, and published the results on Tuesday 3 November1. The auction drew 41 bids for nearly 12,000 reliable megawatts (rMW: output a plant is counted on to deliver in a shortage) against 4,500 tendered, and awarded eleven of them for about 5,160 rMW. None of it runs this winter.
The average award was €155,296 per rMW a year, 36% under the €244,000 cap, so the tranche costs about €801m a year. The last bid accepted was taken in full, 660 rMW over the tender, and BDEW, the German energy industry association, says the excess comes off the next round.
Only about 314 rMW, roughly 6%, went to Bavaria and Baden-Württemberg, the southern states that import power when northern wind drops. Most went to North Rhine-Westphalia, Brandenburg and Saxony. BDEW and Börsen-Zeitung, the German financial daily, report that LEAG, the east German lignite generator, won six awards and RWE, Germany's largest power generator, won three.
The law passed in July with a locational split, a rule dividing awards between north and south, and the regulator launched bidding with no state-aid clearance in hand. The European Commission has since approved the auctions without opening a probe, BDEW reports. "We now have the certainty that this capacity will actually be built," said Klaus Müller, the regulator's president2. On this desk's reading, most of the new capacity sits north of the grid bottleneck that leaves the south short in a lull. Müller sees it the other way: "The regional spread of the winning bids will help to safeguard network operation," he said3.