The Bundestag passed StromVKG on 9 July with SPD votes, raising the capacity-auction bid ceiling 41% to €244,000/MW and splitting new capacity one-third north, two-thirds south.

TechnologyDeveloping
Key takeaway

Germany raised its capacity-auction ceiling 41%, choosing firm-supply certainty over auction price discipline.

The Bundestag passed the StromVKG capacity law in final plenary on Thursday 9 July, the CDU/CSU and SPD carrying it against AfD, The Greens and the Left 1. StromVKG, Germany's electricity capacity-payment statute, commissions 11 GW of new hydrogen-ready gas capacity, with the first 9 GW tendered in two 4.5 GW tranches on 8 September and 22 December 2026 and a network-charge surcharge of €1-3bn a year from 2031.

Committee stage changed the auction economics. The bid ceiling rose from €173,000/MW to €244,000/MW, a 41% increase that lifts the clearing cost operators can bid into 2. A locational split now directs one-third of new capacity to northern Germany and two-thirds to the south, where industrial load concentrates and the retired nuclear fleet once anchored the grid, and barriers for battery-storage bidders were lowered. The arc ran from first reading through the 24 June Anhoerung to committee clearance, where the Greens' hydrogen-conversion motion failed .

The SPD threatened to block this law in April; it passed on 9 July with SPD votes. Raising the ceiling 41% signals that the government expected the September auction to clear thin at the old cap and chose cost certainty over price discipline. Germany is legislating dispatchable backup precisely as its merchant CCGTs whipsaw on the clean spark spread, and the capacity payment funds the firm megawatts that spread will not.

Deep Analysis

In plain English

StromVKG is a new German law, finally passed by the Bundestag on 9 July, designed to make sure Germany has enough back-up power plants for days when wind and solar are not producing much electricity. It works by paying gas-fired power plant operators in advance to have capacity ready, through a competitive auction, rather than only paying them when they actually generate power. The final version raises the maximum price the government will pay in that auction by 41%, and splits where the plants can be built: roughly a third in the north, two-thirds in the south, because the country's power grid cannot easily move electricity between the two regions. All new plants must be able to run on hydrogen by 2045.

Deep Analysis
Root Causes

The 41% bid-ceiling increase responds to a structural gap exposed on 30 June, when the lowest wind week of the year combined with a heat surge to push Germany's day-ahead price to €195/MWh with every incremental megawatt coming from thermal plant. Without enough dispatchable capacity cleared in advance, a renewables-heavy grid repeats that exposure on any low-wind day.

The north-south locational split addresses a separate constraint: Germany's transmission grid cannot move enough power from northern wind and southern demand centres without local generation, which is why the law now pays roughly twice as much capacity to site in the south specifically.

What could happen next?
  • Consequence

    A higher bid ceiling raises the network-charge surcharge German consumers eventually pay for capacity, a cost financed from 2031 estimated at EUR 1-3bn a year.

  • Meaning

    The north-south locational split formally acknowledges that Germany's grid, not just its total generation capacity, constrains supply security.

First Reported In

Update #25 · Qatari LNG strike puts TTF back over EUR 50

Deutscher Bundestag· 10 Jul 2026
Read original
Different Perspectives
ESMC (TSMC-majority joint venture)
ESMC (TSMC-majority joint venture)
ESMC's president said construction remains on schedule after the Dresden fab's topping-out ceremony on 14 September, reported by Focus Taiwan with first process equipment still targeted for the second half of 2027. No first-party ESMC or TSMC statement independently confirms the claim, and the fab remains 70% TSMC-owned inside a project Europe cites as its semiconductor sovereignty case.
Civo
Civo
Civo sold out its Navigate London sovereignty conference on 22 September, drawing about 800 attendees including a sitting MP, a former defence procurement minister and sponsors led by Nokia. Companies House confirms chief executive Mark Boost as Civo's sole person with significant control, British and UK-resident, which answers the ownership question the conference itself is arguing matters.
United States Trade Representative
United States Trade Representative
USTR opened its 2027 National Trade Estimate comment window on 14 September, naming the EU among markets with restrictive technology requirements and inviting submissions on cross-border data rules. The window follows Trump's 24 July Section 301 order into EU digital rules by seven weeks, and unused comments are kept, in USTR's own wording, for future negotiations.
Cohere
Cohere
Cohere published the deal on 16 September without naming a regulator, running the merged company globally under its own brand from dual Toronto and Berlin headquarters. It pledges the combined company will deliver sovereign AI on STACKIT, the Schwarz Group's German platform, aimed at government buyers weighing that offer against Berlin's own anchor-customer signal.
Germany (Federal Government)
Germany (Federal Government)
Digital Minister Karsten Wildberger called the Cohere talks "a very strong signal" and signalled Berlin's readiness to become an anchor customer, now its main lever since equity sits with Cohere. The German side secured a co-headquarters and two Cohere C-suite seats, but the protective-rights terms it pressed for in July remain undisclosed.
Poland
Poland