The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether **Microsoft**, **Alphabet**, **Amazon** and **Meta** preserve their raised 2026 capex guidance through the late-July Q2 earnings cycle now that OpenAI's compute commitment has been visibly trimmed.
From the 16 May briefing · Deadline: late-July
Whether **FERC** publishes the RM26-4-000 NOPR (Notice of Proposed Rulemaking) by end-June, and whether PJM's 18 May filing matches the language FERC accepted on 16 April.
From the 16 May briefing · Deadline: 18 May
Whether the 18-21 May Denver, Seattle and Minneapolis votes produce a majority of refusals, consolidating the municipal moratorium tier into a default posture.
From the 16 May briefing · Deadline: 21 May
Whether OpenAI's pivot to leased compute reroutes Q3 hyperscaler bookings toward **Equinix**, **Digital Realty** and other colocation operators, and whether Crusoe's Abilene inventory finds a second taker.
From the 16 May briefing
The **FERC RM26-4-000** order at end of June: whether it constrains or accelerates large-load interconnection, and how it treats behind-the-meter cost allocation
From the 6 May briefing · Deadline: end of June
Whether any second US state attempts a moratorium after the Maine veto, and whether the Sanders-Ocasio-Cortez federal proposal reaches a committee mark-up
From the 6 May briefing
The **TSJ Aragón** ruling on the Ecologistas en Acción challenge, the first European judicial test of a community data-centre case
From the 6 May briefing
Stargate UAE first-phase commissioning against the Q3 2026 target
From the 6 May briefing · Deadline: Q3 2026
GE Vernova Q2 backlog: any sign of demand revision, or a further extension of the 2030 slot stretch
From the 6 May briefing
Whether **Governor Janet Mills** signs, vetoes or lets the Maine moratorium lapse before the May 2026 decision window closes.
From the 26 Apr briefing · Deadline: May 2026
Whether **Ofgem** publishes its AI-demand consultation response this quarter, the document UK grid analysts treat as the most consequential of the year.
From the 26 Apr briefing
Whether **Synergy Research Group's** Q1 2026 hyperscale figures, due mid-May, confirm or break the $142 billion quarterly capex baseline.
From the 26 Apr briefing · Deadline: Q1 2026
Whether **EirGrid** and **ESB Networks** publish the CRU-mandated data centre connection process or formally explain its absence.
From the 26 Apr briefing
Whether **Stargate UAE** phase 1 commissions on its Q3 2026 schedule or joins the headline-to-ground gap.
From the 26 Apr briefing · Deadline: Q3 2026
Whether the **Tribunal Superior de Justicia de Aragón** admits the Ecologistas en Acción challenge for substantive hearing, setting a Spanish precedent.
From the 26 Apr briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
That spare hydropower sits mostly in the north; in the south, where prices track Germany and Britain, a data-centre booking competes directly with households for the same power.
What was trueNo source in the run's research supports the north/south price split; the sentence was cut from event analysis in review and is removed from the body before sync.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.