Happened · 2

  • Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.

    From the 8 Sept briefing · Judged 22 Oct 2026

    SEA's Alto Jahuel case file is available and was checked.

  • Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.

    From the 8 Sept briefing · Judged 22 Oct 2026

    CRU approved MPID 345 on 22 September 2026.

Unresolved · 1

  • NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .

    From the 24 Sept briefing · Judged 22 Oct 2026

    Final ballot passed; Board adoption and FERC filing remain pending.

Still open · 75

Show the 10 most recent
  • Whether **Microsoft**, **Alphabet**, **Amazon** and **Meta** preserve their raised 2026 capex guidance through the late-July Q2 earnings cycle now that OpenAI's compute commitment has been visibly trimmed.

    From the 16 May briefing · Deadline: late-July

  • Whether **FERC** publishes the RM26-4-000 NOPR (Notice of Proposed Rulemaking) by end-June, and whether PJM's 18 May filing matches the language FERC accepted on 16 April.

    From the 16 May briefing · Deadline: 18 May

  • Whether the 18-21 May Denver, Seattle and Minneapolis votes produce a majority of refusals, consolidating the municipal moratorium tier into a default posture.

    From the 16 May briefing · Deadline: 21 May

  • Whether OpenAI's pivot to leased compute reroutes Q3 hyperscaler bookings toward **Equinix**, **Digital Realty** and other colocation operators, and whether Crusoe's Abilene inventory finds a second taker.

    From the 16 May briefing

  • The **FERC RM26-4-000** order at end of June: whether it constrains or accelerates large-load interconnection, and how it treats behind-the-meter cost allocation

    From the 6 May briefing · Deadline: end of June

  • Whether any second US state attempts a moratorium after the Maine veto, and whether the Sanders-Ocasio-Cortez federal proposal reaches a committee mark-up

    From the 6 May briefing

  • The **TSJ Aragón** ruling on the Ecologistas en Acción challenge, the first European judicial test of a community data-centre case

    From the 6 May briefing

  • Stargate UAE first-phase commissioning against the Q3 2026 target

    From the 6 May briefing · Deadline: Q3 2026

  • GE Vernova Q2 backlog: any sign of demand revision, or a further extension of the 2030 slot stretch

    From the 6 May briefing

  • Whether **Governor Janet Mills** signs, vetoes or lets the Maine moratorium lapse before the May 2026 decision window closes.

    From the 26 Apr briefing · Deadline: May 2026

  • Whether **Ofgem** publishes its AI-demand consultation response this quarter, the document UK grid analysts treat as the most consequential of the year.

    From the 26 Apr briefing

  • Whether **Synergy Research Group's** Q1 2026 hyperscale figures, due mid-May, confirm or break the $142 billion quarterly capex baseline.

    From the 26 Apr briefing · Deadline: Q1 2026

  • Whether **EirGrid** and **ESB Networks** publish the CRU-mandated data centre connection process or formally explain its absence.

    From the 26 Apr briefing

  • Whether **Stargate UAE** phase 1 commissions on its Q3 2026 schedule or joins the headline-to-ground gap.

    From the 26 Apr briefing · Deadline: Q3 2026

  • Whether the **Tribunal Superior de Justicia de Aragón** admits the Ecologistas en Acción challenge for substantive hearing, setting a Spanish precedent.

    From the 26 Apr briefing

What each side claimed

Claims are what a named side said at the time. We record them as said and judge them only against later evidence.

No claims recorded yet.

What we got wrong

Show the 10 most recent
  • MinorCorrected 22 Oct 2026
    We said

    All Irish data centres must ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected data centres.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    Ireland applies MPID 345 to existing sites.

    What was true

    MPID 345 applies to existing transmission-connected sites.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant data centres must seek a derogation.

    What was true

    The derogation route applies to transmission-connected data centres.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant sites must seek a derogation.

    What was true

    The derogation route applies to transmission-connected sites.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant data centres must seek a derogation.

    What was true

    The derogation route applies to transmission-connected data centres.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through faults.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    All non-compliant data centres must seek a derogation.

    What was true

    The derogation route applies to transmission-connected data centres.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 22 Oct 2026
    We said

    MPID 345 requires large users to ride through voltage dips.

    What was true

    MPID 345 applies to transmission-connected demand facilities.

    In CRU makes Irish sites ride through dips

  • MinorCorrected 18 Oct 2026
    We said

    METI's preferred regions for new data centres are Hokkaido and Kyushu.

    What was true

    No government source names preferred regions. The 2026 MIC white paper gives the Kanto and Kinki concentration (about 90%) and the aim of regional distribution; Hokkaido and Kyushu as hubs come from a Mitsubishi Research Institute proposal, not policy.

    In MC Digital Realty breaks ground in Osaka

  • MinorCorrected 18 Oct 2026
    We said

    Suaram provided the platform for Kua Kia Soong's moratorium call

    What was true

    Kua Kia Soong made the call in a personal letter published by Free Malaysia Today on 26 June 2026, signed as a former MP and former Suaram director; Suaram took no part

    In Malaysia urged to halt data centres

  • MinorCorrected 18 Oct 2026
    We said

    The multiple is at the top of emerging-market infrastructure valuations

    What was true

    The multiple rested on an unsourced EBITDA figure; the comparison is removed

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Teraco enterprise value $4.1bn, about 28x a publicly disclosed 2025 EBITDA of $145m

    What was true

    $650m for 16 percentage points implies an equity value of about $4.1bn; no public source for a $145m EBITDA was found

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Digital Realty has an enterprise value of roughly $50bn and the deals are 3% of it

    What was true

    No source supports the $50bn figure; the claim is removed

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June

    What was true

    On 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June

    What was true

    On 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June

    What was true

    On 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June

    What was true

    On 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed

    In Digital Realty agrees to lift Teraco to 77%

  • MinorCorrected 18 Oct 2026
    We said

    Teraco operates in South Africa, Nigeria and Kenya

    What was true

    Teraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses

    In Digital Realty agrees to lift Teraco to 77%