The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentFERC rules on a large-load plan: By 31 January 2027, FERC issues an order accepting at least one of the large-load plans the six grid operators filed between 13 and 20 November, with conditions allowed.
From the 26 Nov briefing · Deadline: 2027-01-31
Alberta passes Bill 42: By 31 December 2026, Alberta's legislature passes Bill 42, with its 600 m setback from homes and its exemption for projects already approved and those before the commission.
From the 26 Nov briefing · Deadline: 2026-12-31
Spain repeals its decree: By 30 June 2027, Spain's government repeals the data-centre royal decree approved on 20 November 2026, ending the 80% hourly renewables test.
From the 26 Nov briefing · Deadline: 2027-06-30
Brazil Redata decree: Brazil publishes the Redata implementing decree in the Diário Oficial da União by 30 November.
From the 15 Nov briefing · Deadline: 2026-11-30
NEXTDC spill: No spill meeting is called at NEXTDC's annual meeting on 20 November.
From the 15 Nov briefing · Deadline: 2026-11-20
Irish High Court: The Irish High Court gives judgment on the challenge to the CRU's large energy users connection policy by 31 March 2027.
From the 15 Nov briefing · Deadline: 2027-03-31
Norway concession scheme: Norway's government sends its data-centre concession scheme out for public consultation by 31 March 2027.
From the 15 Nov briefing · Deadline: 2027-03-31
Loudoun pause: Loudoun County's supervisors adopt the 12-month pause on new data-centre and substation applications at their meeting on 17 November.
From the 22 Oct briefing · Deadline: 2026-11-17
NEXTDC sites: NEXTDC announces the sale of at least one development site by its annual meeting on 20 November.
From the 22 Oct briefing · Deadline: 2026-11-20
Korea grid code: South Korea issues its AI data-centre grid code by 31 December with a transition period for projects already under way.
From the 22 Oct briefing · Deadline: 2026-12-31
Brazil: Whether ANEEL rules on Pahlavan's injunction requests, due within 48 hours of the 6 October order but unpublished by 17 October, and whether awards at the Replan substation must be redone
From the 18 Oct briefing · Deadline: within 48 hours
Spain: Whether the Consejo de Ministros approves the data-centre decree before the 29 November election, and whether hourly renewable matching survives
From the 18 Oct briefing · Deadline: 29 November
Norway: Whether the Storting's Energy and Environment Committee recommends any part of Dok 8:6 S, such as a parliamentary vote on 25 MW projects
From the 18 Oct briefing
Oregon: Whether DEQ adopts the requested pause, and whether it applies it to permit applications already filed, which the letter does not exempt
From the 18 Oct briefing
Scottish Ministers' decision on the Redheughs Avenue appeal (PPA-230-2794), and whether they apply the Direction to it .
From the 24 Sept briefing
A court challenge to the TCEQ pause, and the exemptions TCEQ sets out in its 19 October compliance report .
From the 24 Sept briefing · Deadline: 19 October
Spain's final decree: hourly matching either survives or gives way to an annual test .
From the 24 Sept briefing
Scottish Ministers' decision on the recalled Redheughs Avenue appeal, appeal reference PPA-230-2794, against a 28 September target date.
From the 8 Sept briefing · Deadline: 28 September
Whether President Lula sanctions PL 278/2026 unchanged, and whether ANEEL (Brazil's federal electricity regulator) or the national system operator say how demand conditioned on renewable supply will be served.
From the 8 Sept briefing
Any appeal lodged against the Cape Town Equinix approval, by the Legal Resources Centre or another party.
From the 8 Sept briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- SignificantCorrected 22 Oct 2026We said
Existing data centres in Seattle keep their current connections and can expand under pre-moratorium rules. Only new proposals above 20 MVA are blocked.
What was trueExisting data centres can keep operating. An expansion exemption permits at most another 20 MVA at eligible existing facilities; larger expansions also face the pause.
- SignificantCorrected 22 Oct 2026We said
voted unanimously on 9 and 10 June to stop
What was truevoted unanimously on 9 June, with the mayor signing on 11 June, to stop
- SignificantCorrected 22 Oct 2026We said
The ordinance exempts Seattle's existing data centres, which may keep expanding under current rules, so the freeze bites only on new arrivals.
What was trueQualifying operating facilities can continue operating. Their expansion exemption is limited to an additional **20 MVA**, so larger expansions also fall under the moratorium.
- SignificantCorrected 22 Oct 2026We said
making the freeze legally binding rather than provisional
What was truewith the ordinance taking effect when the mayor signed on **11 June**
- SignificantCorrected 22 Oct 2026We said
voted **9 to 0** on **9 and 10 June** to enact
What was truevoted **9 to 0** on **9 June** to approve
- SignificantCorrected 22 Oct 2026We said
voted 9 to 0 on 9 and 10 June to enact
What was truevoted 9 to 0 on 9 June to approve
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9-0 on 9 and 10 June. The vote made its 365-day moratorium legally binding on new loads above 20 MVA
What was trueSeattle's City Council approved its 365-day moratorium 9-0 on 9 June. It took effect with the mayor's signature on 11 June and applies to defined data centres above 20 MVA
- SignificantCorrected 22 Oct 2026We said
Existing data centres are exempt and may expand under current rules.
What was trueOperating facilities may continue, but the expansion exemption is limited to an additional 20 MVA; larger expansions are subject to the moratorium.
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9 to 0 on 9 and 10 June to enact the 365-day moratorium it had introduced on 30 April, making the freeze legally binding.
What was trueSeattle's City Council approved the proposed 365-day moratorium by 9 votes to 0 on 9 June. The ordinance took effect with the mayor's signature on 11 June.
- MinorCorrected 22 Oct 2026We said
The CRU decision text had not been checked.
What was trueCRU2026145 and CRU2026145c confirm the scope, date and derogation route.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
The exact start date lacked primary confirmation.
What was trueCRU's approval letter confirms the effective date as 27 October 2026.
- MinorCorrected 22 Oct 2026We said
All non-compliant sites must seek an exemption.
What was trueOnly sites covered by MPID 345 need a derogation.
- MinorCorrected 22 Oct 2026We said
MPID 345 applies to large electricity users generally.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All Irish data centres need an exemption if they cannot comply.
What was trueMPID 345 applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek an exemption.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.