Data Centres: Boom and Backlash
17JUN

Berry Hill approval hinges on tax deal

2 min read
10:13UTC

Danville and Pittsylvania County officials approved an AI data centre at the Berry Hill megasite on 26 May, then attached the consent to Virginia's unresolved tax exemption fight, the first local approval formally conditioned on state fiscal policy.

IndustryDeveloping
Key takeaway

Berry Hill's approval now hangs on Richmond's budget vote, the same tax uncertainty that cancelled the Compass sites.

On 26 May, Danville and Pittsylvania County officials approved an AI data centre at the Berry Hill megasite in southern Virginia, then made the approval explicitly contingent on the outcome of the state tax exemption standoff. 1 The vote conditions local consent on a fiscal decision that sits with the legislature, not the planners.

The contingent structure follows the same legislative leverage that the spring zoning fights exposed. Fairfax voted 8-2 for tighter data-centre rules and Sabey withdrew its Seattle request in the same window . Those fights reached projects at the planning stage. Berry Hill cleared its planning hurdle, yet local approval no longer settles the matter: the same tax uncertainty that drove Compass to abandon its Greensville County and Emporia searches now follows projects past the point of local consent.

Lawmakers led by Louise Lucas are pressing to end the abatement by 2026 against a House preference for 2035. Until that resolves, an approved project in Virginia carries an open fiscal question that the county vote cannot close.

Deep Analysis

In plain English

Berry Hill is a large undeveloped industrial site in southern Virginia that straddles the city of Danville and Pittsylvania County. Local officials voted on 26 May to approve an AI data centre there, which would normally mean the developer could start planning construction. But they attached an unusual condition: the approval only holds if Virginia's state government resolves its tax exemption dispute in a way that keeps the incentive alive. If the Senate Finance chair wins and the exemption ends in 2026, the Berry Hill project effectively collapses despite the local yes vote. This is unusual because local planning decisions normally depend only on planning criteria: traffic, noise, land use, and utilities. By tying the vote to a state fiscal outcome, Berry Hill's local officials are acknowledging that no one can build a viable business case for the project without the tax certainty that Richmond has not yet provided.

Deep Analysis
Root Causes

Berry Hill's contingent structure reflects a fundamental mismatch in Virginia's governance architecture: local planning authorities control land use but have no role in the state fiscal policy that determines whether a project is economically viable.

A local yes vote and a state legislative deadlock operate on entirely separate tracks, which the Berry Hill approval has now made explicitly visible by tying them together.

What could happen next?
  • Precedent

    The Berry Hill conditional structure may spread to other Virginia localities facing similar pipeline decisions, effectively pausing new local approvals until Richmond resolves the budget standoff.

  • Risk

    A state fiscal settlement that partially preserves the exemption may leave Berry Hill's conditional approval in legal ambiguity, requiring fresh local votes to activate the consent.

First Reported In

Update #4 · Grid wins power to switch off data centres

Cardinal News· 26 May 2026
Read original
Different Perspectives
Government of Odisha
Government of Odisha
Odisha signed a $1.5bn agreement with HCLTech and Sarvam AI on 24 July for a sovereign AI data centre in Bhubaneswar, targeting 2028 operations. While regulators elsewhere price developers out of the queue, Odisha is bidding state financial assistance to bring capacity in, betting the AI infrastructure boom is worth courting rather than rationing.
Switch Datacenters and Uithoorn
Switch Datacenters and Uithoorn
The developer, the municipality, Liander and dozens of greenhouse growers signed a waste-heat agreement letting a 60 MVA facility proceed under a provincial rule that bans sites above 5 MVA. The public-interest exception argues the site relieves rather than adds to grid congestion, working around a standing ban from inside rather than waiting for it to change.
Iskandar Puteri residents
Iskandar Puteri residents
Residents protested in February over falling water pressure they attribute to ZDATA's 300 MW construction; ZDATA disputes causation and has not yet resolved the dispute with its wastewater-only pivot. The complaint sits unadjudicated while the operator advertises compliance to state authorities the residents cannot address directly.
Microsoft
Microsoft
DC Byte reports Microsoft looking to the Nordics for new capacity while Dublin's regional share falls to 15 per cent, though this is a market-intelligence inference rather than a company statement. Microsoft keeps its existing Dublin cloud region, which is costly to relocate, while directing new investment where power is cheaper and the queue is shorter.
ISO New England
ISO New England
ISO-NE proposed excluding new large loads from its Installed Capacity Requirement entirely, forcing data centres to bring their own generation or accept curtailment, even though New England's demand has been flat or falling for a decade. The reform is pre-emptive, written before the region has felt the strain PJM and MISO already report.
Ofgem
Ofgem
Ofgem opened its Data Centre Commitment Fee consultation on 29 July, arguing that free options on grid capacity let developers bank places on ten sites and abandon nine, crowding out projects that would build. It expects the deposit to filter the queue before the rule even takes final form.