Skip to content
You can now search across every topic, entity and event.What's new
Data Centres: Boom and Backlash
26MAY

Hill County folds, lawsuit lives on

3 min read
11:34UTC

Hill County, Texas rescinded its data-centre moratorium on Thursday 4 June, seven days after developer RCM Hill sued it for $100 million. The suit is still live.

IndustryDeveloping
Key takeaway

A $100m taking suit reversed a Texas data-centre ban in a week, before any judge ruled on it.

Hill County, Texas voted unanimously on Thursday 4 June to rescind its moratorium on data-centre development, not because a court ordered it but to cap taxpayer liability. The county had blocked RCM Hill LLC's 1,235 MW Project Aquila campus near Hillsboro; on Thursday 28 May the developer sued for $100 million, calling the freeze an unconstitutional taking of property . Seven days later the county folded. 1

Rescinding the moratorium did not end the litigation. RCM Hill still seeks a court declaration that the original freeze was unlawful, plus damages dated from the day it passed. That keeps the Fifth Amendment taking question alive even with no moratorium left to challenge. The Fifth Amendment bars government from taking private property without compensation, and developers are now testing whether a building freeze counts as exactly that. A ruling for RCM Hill would chill every other county weighing a ban.

The county did not abandon oversight altogether. It replaced the moratorium with disclosure rules: applicants must now declare water use, traffic, noise and economic effect, and notify the public more widely than before.

Three moratoriums have now fallen by three different routes. Maine's first-in-nation statewide ban fell to a governor's veto ; Prince William County's fast-track rezoning fell to an appellate court ; Hill County fell to a single lawyer's letter. Each consent tool has met a sharper instrument of restraint, and developers have learned that the threat of a ruling can work faster than the ruling itself.

Deep Analysis

In plain English

Hill County in rural Texas voted to block all new data-centre construction in 2026. A developer called RCM Hill had been planning a giant computer campus there, called Project Aquila, that would have used as much electricity as a city of roughly 900,000 homes. The county freeze stopped all construction. Seven days after RCM Hill sued the county for $100 million, claiming the freeze illegally took away its property rights under the US Constitution, the county reversed course and voted unanimously to lift the ban. The lawsuit is still alive: RCM Hill still wants compensation for the time its project was blocked. The case shows that a rural county with a small budget faces a very unequal legal fight when it tries to stop a billion-dollar data-centre project without a clear legal basis for doing so.

Deep Analysis
Root Causes

Hill County's original moratorium reflected a common pattern in rural Texas counties: a large-scale industrial project arrives with insufficient advance engagement, local officials face constituent pressure and respond with a blanket freeze rather than a structured review process. The county had no pre-existing land-use framework for facilities drawing more than 200 MW, so the moratorium was the default response in the absence of a permitting mechanism.

Project Aquila at 1,235 MW would have drawn roughly 1.5% of ERCOT's peak demand from a single rural county, an impact scale that requires a genuine public-interest analysis rather than a blanket halt.

RCM Hill's $100 million lawsuit converts the county's failure to design a permitting process into a direct fiscal liability, which is why the rescission came before any court hearing: the county's legal counsel almost certainly calculated that defending the moratorium in federal court was more expensive than permitting the project.

What could happen next?
  • Precedent

    RCM Hill's pre-adjudication reversal establishes that a federal taking lawsuit is sufficient deterrent to force rescission without a court ruling, lowering the bar for other developers facing rural moratoriums.

    Short term · Assessed
  • Risk

    Rural counties across Texas and other ERCOT states with no large-load permitting frameworks face the same asymmetric litigation exposure if they impose blanket moratoriums rather than structured review processes.

    Medium term · Assessed
  • Consequence

    The active damages claim creates an unresolved legal question on the quantum of loss for data-centre downtime, which could establish a precedent figure that all future taking claims cite.

    Medium term · Reported
First Reported In

Update #6 · Oregon bills data centres, not homes

Texas Tribune· 10 Jun 2026
Read original
Causes and effects
This Event
Hill County folds, lawsuit lives on
A developer reversed a county ban using the threat of a constitutional ruling rather than a ruling itself, a faster lever than any electoral or appellate route.
Different Perspectives
Global hyperscale operators
Global hyperscale operators
Operators are still filing gigawatt-scale campuses and Meta is proceeding with its $10bn Lebanon, Indiana site despite the county-level bans nearby, betting Q2 capex outruns the patchwork of restrictions. Industry framing casts New York's freeze, Oregon's surcharge and Indiana's bans as taxes and levies that push build-out toward faster-permitting jurisdictions such as India and the Gulf.
EirGrid
EirGrid
EirGrid set a 900 MW instantaneous demand-loss ceiling because a single voltage dip can trip many data centres onto backup power at once, risking imbalance above 1,150 MW. It wrote the limit into a standing procedure rather than waiting for an emergency to force one.
US host communities and ratepayers
US host communities and ratepayers
Prince William residents backed the 8-0 denial of Dulles South over the Occoquan watershed, drinking water for eight million people, while Oregon's approved tariff cuts residential bills 1.3% by charging large loads 29% more. Their position: consent and cost-attribution belong in law, not left to a developer's or a utility's discretion.
Hassan Allam Digital Infrastructure
Hassan Allam Digital Infrastructure
Hassan Allam Digital Infrastructure, an Egyptian conglomerate rather than a foreign hyperscaler, reportedly secured a domestic hyperscale licence with a $400m first phase, per single-source reporting still to be verified. It reads as home-grown sovereign compute ambition, building national capacity rather than importing a US or Gulf operator's campus.
Damac Digital
Damac Digital
Damac Digital keeps building toward roughly 6,000 megawatts of hyperscale capacity across 13 countries while Virginia taxes power and New York weighs a freeze. Every dollar or month of delay a US state adds is capacity a Gulf developer can site somewhere with faster permitting and no equivalent levy.
Acequia communities, Santa Fe County
Acequia communities, Santa Fe County
Santa Fe County commissioners voted unanimously on 2 July to freeze any data centre over one megawatt, citing the acequia irrigation commons that has shared scarce water since Spanish colonial rule. They expect the low threshold to draw the same Fifth Amendment challenge RCM Hill brought against Hill County, Texas.