Trebbin, a town in Brandenburg south of Berlin, reported on 7 October that work has begun on two data-centre buildings and a substation under building permits already granted1. The operating permit, required under Germany's Federal Immission Control Act for plant that emits pollution or noise, is still under review by the state environment agency, the Landesamt für Umwelt Brandenburg. The building permits let the structures go up; only the operating permit lets the site run. Brussels is adding its own layer: in September the European Commission adopted an A-to-G energy rating scheme meant to grade large EU data centres from 2027.

Trebbin data centre starts before permit
The Brandenburg town of Trebbin said on 7 October that work has begun on two data-centre buildings and a substation while the state still reviews the operating permit.
Construction began at Trebbin before Brandenburg decided the data centre's operating permit.
Deep Analysis
Trebbin is a small town south of Berlin, in the German State of Brandenburg. A company has started building two data centres there, plus a substation, the equipment that connects them to the power grid. The town gave building permits. But the data centres also need a separate permit to operate, because their backup generators produce fumes and noise. Brandenburg's environment agency is still checking that application, so the buildings may go up before anyone knows the final operating rules.
Brandenburg offers land, wind and solar output and proximity to Berlin's network hubs, which draws data centres from the constrained Frankfurt market. The state's permitting agency is the bottleneck for operating approvals, not the town's building permits.
Germany's Energy Efficiency Act of 2023 adds efficiency and waste-heat duties for new data centres. Those rules sit alongside the immission permit, so a project in Brandenburg must clear both national efficiency standards and state emission review before it can run.
- Risk
The operating permit may impose conditions on generators or fuel storage after construction has begun.
- Consequence
Brandenburg may draw more data-centre projects that would otherwise wait for capacity around Frankfurt.