Data Centres: Boom and Backlash
15JUL

UK Gate 2 grid offers begin issuing

4 min read
13:16UTC

NESO issued the first transmission connection offers under the reformed UK queue in mid-May, with AI Growth Zones drawing priority access, electricity discounts and the right to build their own high-voltage infrastructure.

IndustryDeveloping
Key takeaway

Gate 2 starts issuing; the electricity discount decides whether UK siting can compete with the Nordics again.

NESO (National Energy System Operator) began issuing the first transmission connection offers under the reformed UK queue this week, with Gate 2 Phase 1 opening against an applications book that exceeds Britain's 45 GW national peak. The framework was set on Wednesday 11 March, when energy minister Michael Shanks and AI minister Kanishka Narayan confirmed that AI Growth Zones would receive priority access, 'significant discounts on electricity bills' and the right for developers to build their own high-voltage lines and substations⁠1. The Gate 2 issuance turns those concessions from a policy paper into a queue place.

OpenAI's quantification of UK industrial electricity at four times US and Nordic rates sets the cost gap Gate 2 alone cannot close, and which has driven greenfield siting decisions to Texas and Finland since 2024. The new electricity discount is the concession that addresses it directly, and the self-build right for high-voltage lines is what makes the discount usable: an operator that can construct its own substation does not need to wait for NESO's distribution allocation to commission the load.

The demand-side application volume that produced the queue grew 460% in six months to June 2025, and the worst waits reached 15 years before the reforms⁠2. Gate 2 Phase 1 sets the test of whether the financial-deposit reforms cleared the speculative-application backlog NESO had identified as the structural cause. If the offers being issued this month match the pre-Gate 2 forward demand, the reform has worked at the procedural layer. The harder test is whether the AI Growth Zone discount has rebuilt the UK's economic case enough to claw back any of the Cobalt Park-style sites OpenAI has now paused. The earliest signal will come from the second tranche of offers and from which AI Growth Zone operators show up at NESO's connection desk in June.

Deep Analysis

In plain English

Britain has a huge backlog of companies waiting to connect to the electricity grid: more than 45 gigawatts of requests from data centres alone, which is more than the entire country uses at peak demand. This queue has caused waits of up to 15 years for a new connection. The government has introduced a reformed system called Gate 2, which started issuing connection offers in May 2026. Companies that have seriously committed to building will now get priority. Data centres in specially designated zones called AI Growth Zones also get a discount on their electricity bills and the right to build their own electricity lines and substations, bypassing some of the queue entirely.

Deep Analysis
Root Causes

The UK grid queue grew 460% in six months to June 2025, from roughly 10 GW to 50 GW, because the queue had no financial deposit requirement: speculative applicants could hold a position for three to five years at near-zero cost, crowding out committed developers.

The Gate 2 reform introduced financial deposits and active curation of the queue, removing the speculative applications that had inflated the backlog. The 460% growth figure itself is the root cause, not a symptom: it reflects that the pre-Gate 2 queue was not a demand signal but an option-holding exercise.

The AI Growth Zone self-build right for high-voltage lines and substations addresses the deeper structural constraint: NESO's distribution allocation is the bottleneck below the transmission level.

An operator that can construct its own substation and HV lines does not need to wait for NESO's distribution capacity to be available; it bypasses that layer entirely and connects directly to the transmission network. This is the more consequential concession for operators already planning 100 MW-plus campuses with the capital to self-fund substation construction.

What could happen next?
  • Opportunity

    UK AI Growth Zone operators with confirmed Gate 2 positions and the capital to self-build HV infrastructure face a 2-3 year payback advantage over a comparable Finnish build, making the UK competitive for the first time since 2024.

    Medium term · 0.65
  • Risk

    The 460% queue growth figure confirms that most pre-Gate 2 applicants were speculative; if the post-deposit queue is significantly smaller than 50 GW, the reform may reveal that committed UK data-centre demand is far below the headline backlog.

    Short term · 0.7
  • Consequence

    NESO's Gate 2 offers are the first test of whether the UK's queue reform can close the 15-year wait that drove OpenAI to pause Cobalt Park (ID:2785); the second tranche of offers in June-September will be the cleaner signal.

    Short term · 0.8
First Reported In

Update #3 · OpenAI cuts $800bn; rivals double down

GOV.UK / DESNZ· 16 May 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.