Gate 2 Phase 1
ConceptGB

Gate 2 Phase 1

First tranche of GB's reformed grid connections queue for sites meeting Ofgem's readiness criteria.

Gate 2 Phase 1 is the first tranche of Britain's reformed grid connections queue, live since NESO began issuing offers in mid-May 2026. A connection attaches to whoever holds secured land rights, typically the site developer rather than a leasing tenant.

Last refreshed: 14 August 2026

Key Question

Who holds a Gate 2 connection when a tenant leases capacity from the site owner?

Timeline for Gate 2 Phase 1

#13 12 Aug
#3 13 May
View full timeline →

Background

Gate 2 Phase 1 is the first tranche of Great Britain's reformed transmission connections queue, launched after Ofgem approved the Gate 2 Criteria Methodology in April 2025. NESO began issuing the first offers under the reform from mid-May 2026, giving AI Growth Zones priority access and bill discounts against a queue that had grown past 45 GW, more than the country's entire peak demand.

A Gate 2 offer requires secured land rights over a project's site boundary plus strategic alignment. It attaches to whoever holds those rights, typically the site developer rather than a tenant leasing capacity within an already-connected campus. Vantage Data Centers' Newport lease to Nebius illustrates the split: Vantage holds the site's grid position, and Nebius contracts with it commercially rather than acquiring a connection of its own.

Projects with agreements to connect by 31 December 2027 keep their Phase 1 queue position as 'protected projects'. Neither Ofgem nor NESO publishes a distinct capacity threshold or eligibility test separating Phase 1 from Gate 2 more broadly.

Common Questions
What is Gate 2 in Britain's grid connections reform?
Gate 2 is the tranche of NESO's reformed transmission connections queue that grants confirmed offers to projects meeting Readiness Criteria (secured land rights) and Strategic Alignment Criteria.Source: Ofgem Gate 2 Criteria Methodology Final Decision
Who holds a Gate 2 connection offer in a shared data-centre campus?
The offer attaches to whoever holds secured land rights over the site, typically the campus developer, rather than a company leasing rack space within it.Source: Ofgem Gate 2 Criteria Methodology Final Decision
When did NESO issue Britain's first Gate 2 offers?
NESO began issuing Gate 2 offers under the reformed queue from mid-May 2026, following Ofgem's April 2025 approval of the Gate 2 Criteria Methodology.Source: NESO connections reform documents
What happens to protected projects under Gate 2 Phase 1?
Projects with agreements to connect on or before 31 December 2027 keep their existing queue position within Phase 1 as 'protected projects'.Source: Ofgem Gate 2 Criteria Methodology Final Decision