Data Centres: Boom and Backlash
15JUL

Five US moratorium votes in seven days

4 min read
13:16UTC

Camden County Georgia enacted a 9-month freeze on Tuesday 5 May; Normal Illinois, Denver, Seattle and Minneapolis all hold their own moratorium votes in the week beginning Friday 15 May.

IndustryDeveloping
Key takeaway

Maine's veto pushed the moratorium fight below the state line, and five separate councils now decide it in seven days.

Camden County, Georgia enacted a 9-month data-centre moratorium on Tuesday 5 May, the first local pause in a state operators had treated as a clean political runway⁠1. Normal, Illinois voted on a 6-month pause on Friday 15 May. Denver votes Monday 18 May on a one-year moratorium that would take effect three days later if approved. Seattle's Parks and City Light Committee and Land Use and Sustainability Committee both meet on Wednesday 20 May to vote on the 365-day freeze introduced on 30 April after City Light received 369 MW of new connection requests. Minneapolis votes Thursday 21 May, alongside Minnesota's HF 4888 statewide pause. South Dakota's SB 135, which authorises local governments to ban data-centre construction outright, has already passed.

The vote calendar lands two weeks after Maine Governor Janet Mills vetoed LD 307 and the House sustained the veto on Wednesday 29 April. The veto did not slow the movement; it relocated it to a jurisdictional layer where no single industry lobbying campaign can contain it. Good Jobs First tracks 11 active state bills and dozens of enacted local pauses; the datacenterbans.com tracker now updates weekly. The South Dakota authorisation model is the most consequential of the lot: a state legislature voluntarily ceding the right to pre-empt local bans converts every county hearing into a potentially binding moratorium vote.

The industry's communications case rests on the job-creation argument used in Camden County and lost. A commissioned hyperscale campus typically employs a few dozen staff, a figure that maps poorly onto the construction-jobs framing that builds local political support for refineries or auto plants. Lobbying capacity built to contest one state house at a time now has to run dozens of city-council fights in parallel, with the tax-abatement case making a weaker showing at municipal scale than under a state-level subsidy umbrella. The 18-21 May results will signal whether Camden County is the lead indicator or the outlier.

Deep Analysis

In plain English

Cities across the United States are voting on whether to stop new data centres being built in their areas, at least temporarily. Camden County in Georgia voted yes in early May. Normal in Illinois, Denver, Seattle and Minneapolis all had votes scheduled within a single week in May 2026. This wave of local opposition follows a failed attempt to get a statewide ban in Maine: the governor vetoed that bill in late April. When the state-level route closed, opponents moved to city and county level instead, where each local council can make its own rules. A Gallup poll found that 71% of Americans oppose having a data centre built near them.

Deep Analysis
Root Causes

The shift from state to municipal is driven by two structural features of US land-use law. First, data-centre zoning is almost universally a local planning function: state economic-development agencies can offer subsidies but cannot override local zoning boards on permitted use.

Second, municipal utilities, particularly those with public ownership like Seattle City Light, give city councils a direct service-denial lever that bypasses the planning system entirely, connecting the moratorium to utility infrastructure rather than zoning law.

The tax-abatement case that industry communications rely on is also weaker at municipal scale: state-level abatements are negotiated by economic-development agencies with year-round staff and multi-year modelling capacity. Municipal councils face the same developers with far less institutional preparation, and the Camden County result suggests the Loudoun tax-abatement playbook does not transfer without the subsidy infrastructure behind it.

What could happen next?
  • Consequence

    Industry lobbying capacity, built for one state legislature at a time, must now contest dozens of simultaneous city and county hearings with no single coordinating authority.

    Short term · 0.85
  • Risk

    South Dakota SB 135's pre-emption waiver model, if adopted by further state legislatures, removes the fallback that industry has relied on when losing local fights.

    Medium term · 0.7
  • Precedent

    A majority of 'no' votes across the 18-21 May calendar would establish a municipal moratorium posture as the default US local response to large data-centre proposals, regardless of state policy.

    Short term · 0.65
First Reported In

Update #3 · OpenAI cuts $800bn; rivals double down

MultiState· 16 May 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.