Skip to content
You can now search across every topic, entity and event.What's new
Seattle City Council
OrganisationUS

Seattle City Council

Seattle's nine-member legislative body; voted 9-0 on 9-10 June 2026 to enact a 365-day moratorium on new data centre loads above 20 MVA.

Last refreshed: 17 June 2026 · Appears in 1 active topic

Key Question

Does Seattle's enacted moratorium give other cities a legal template FERC cannot override?

Timeline for Seattle City Council

#710 Jun

Voted 9-0 on 9-10 June to enact a 365-day moratorium on new loads above 20 MVA

Data Centres: Boom and Backlash: Seattle locks in its data-centre freeze
#230 Apr

Introduced 365-day emergency moratorium on data centres above 10 MW on 30 April 2026

Data Centres: Boom and Backlash: Seattle freezes data centres for a year
View full timeline →
Common Questions
What is Seattle's emergency data centre moratorium?
Seattle City Council members introduced a 365-day emergency moratorium on new data-centre loads above 10 MW on 30 April 2026, after four developers requested 369 MW for five facilities in a single week from the city's utility, Seattle City Light.Source: Seattle City Council
Why did Seattle City Council freeze new data centres in 2026?
Four developers approached Seattle City Light in a single week requesting power for five facilities totalling 369 MW. The pace of demand prompted the council to introduce a one-year freeze while the city assesses infrastructure capacity.Source: Seattle City Council
What is Seattle City Light and how does it relate to the data centre moratorium?
Seattle City Light is Seattle's city-owned electricity utility. When four developers approached it in a single week in late April 2026 requesting power for five data-centre facilities totalling 369 MW, the pace triggered Seattle City Council to introduce a 365-day emergency moratorium on new loads above 10 MW.Source: Seattle City Council

Background

Seattle City Council voted 9 to 0 on 9 and 10 June 2026 to enact a 365-day moratorium on new data centre loads above 20 MVA (megavolt-amperes, roughly the draw of 16,000 homes), converting the emergency ordinance it introduced on 30 April into binding law. Existing data centres are exempt and may expand under current rules. The enacted ordinance added a delivery calendar absent from the introduction: Seattle City Light must propose rate and capacity changes by 1 July, and Seattle Public Utilities must deliver a water-usage assessment by 30 October. Seattle now joins more than 70 US cities and counties with active bans or pauses.

The Seattle City Council is the nine-member legislative body of Seattle, Washington, with seats elected by district since 2015. It controls Seattle City Light, the municipally-owned utility that serves the city, giving the council direct leverage over power supply to new loads without needing to act through the state legislature or FERC. The moratorium was triggered when four developers approached Seattle City Light in a single week requesting power for five facilities totalling 369 MW, enough for roughly 300,000 homes. At least two developers withdrew before the ordinance passed. Mayor Katie Wilson had announced initial executive steps on 1 May.

Seattle's use of municipal utility authority to block data-centre loads is being watched across the US as a mechanism that FERC's RM26-4-000 order cannot reach. The binding delivery dates for City Light and SPU transform the moratorium from a freeze into an active review process with accountable milestones.

More questions
How many cities in the US have data centre moratoriums in 2026?
As of April/May 2026, dozens of US municipalities have implemented construction pauses, according to Good Jobs First. In a single week in late April, Twinsburg (Ohio), Ypsilanti (Michigan), and Seattle (Washington) all acted, with Seattle's council also considering a formal ordinance.Source: Good Jobs First / Seattle City Council
Did Seattle City Council pass the data centre moratorium?
Yes. Seattle City Council voted 9-0 on 9-10 June 2026 to enact a 365-day moratorium on new data centre loads above 20 MVA, making the freeze legally binding. Existing data centres are exempt.Source: Seattle City Council
What is the threshold for Seattle's data centre ban?
The enacted ordinance bans new or expanded data centre loads above 20 MVA (megavolt-amperes, roughly the draw of 16,000 homes). The introduction had proposed a 10 MW threshold; the enacted ordinance uses 20 MVA.Source: Seattle City Council
Why did Seattle impose a moratorium on data centres?
Four developers approached Seattle City Light in a single week requesting power for five facilities totalling 369 MW, enough for roughly 300,000 homes. The council introduced the 365-day moratorium on 30 April 2026 and enacted it 9-0 on 9-10 June.Source: Seattle City Council
What must Seattle City Light do during the moratorium?
Under the enacted ordinance, Seattle City Light must propose rate and capacity changes by 1 July 2026, and Seattle Public Utilities must deliver a water-usage assessment by 30 October 2026.Source: Seattle City Council
Source Material