New South Wales

Australian state that introduced the Electricity Infrastructure Investment Amendment Bill 2026.

On 5 August, New South Wales introduced a bill allowing its energy minister to approve or block grid connections for electricity users drawing 5 MW or more.

Last refreshed: 24 September 2026 · Appears in 1 active topic

Key Question

Can New South Wales now block a data centre's grid connection outright?

Timeline for New South Wales

#15 22 Sept

Took a related grid power in August

Data Centres: Boom and Backlash: Victoria makes data centres bring power
#13 4 Aug

Introduced a bill letting its energy minister authorise or prohibit large-load grid access

Data Centres: Boom and Backlash: NSW gives its minister a grid veto
View full timeline →

Background

New South Wales is an Australian state whose energy policy matters to data-centre developers seeking large grid connections. On 5 August, it introduced legislation that would let its energy minister authorise or prohibit access schemes for electricity users drawing 5 MW or more.

The threshold reaches beyond hyperscale campuses to suburban colocation facilities and large enterprise sites. The proposed regime also places network-upgrade costs on the connecting developer rather than consumers generally. This gives the state a durable role in deciding how fast major new electricity demand can connect to its network.

Common Questions
What is the NSW Electricity Infrastructure Investment Amendment Bill 2026?
A bill introduced 5 August 2026 letting the state energy minister declare large-load access schemes that can authorise or block grid connections of 5 MW or more.Source: NSW Parliament
Who pays for network upgrades under NSW's new large-load bill?
The minister can allocate network-upgrade costs to the connecting large-load facility rather than spreading them across all consumers.Source: NSW Parliament
What size data centre does the NSW bill target?
Facilities capable of drawing 5 MW or more.Source: NSW Parliament