
Hammerfest LNG
Norway's only Arctic seaborne LNG export terminal, on Melkoya island; operated by Equinor at roughly 4.3 Mtpa.
A valve fault halted Hammerfest LNG late on 8 May 2026, with a restart set for 13 May. Equinor then moved the plant's planned maintenance from 8-11 June to 13-16 June, a three-day stop.
Last refreshed: 28 September 2026 · Appears in 1 active topic
Why does one Arctic LNG plant matter to Europe's gas balance?
Timeline for Hammerfest LNG
Mentioned in: LNG carriers run under a separate cap
European Energy MarketsEquinor takes FID on Troll TWIN
European Energy MarketsHammerfest LNG starts three-day planned maintenance
European Energy MarketsMentioned in: TTF closes above €50 on Iran re-rate
European Energy MarketsMentioned in: May heatwave squeezes injection to 0.3 pp/day
European Energy MarketsBackground
Hammerfest LNG is Equinor's Liquefied Natural Gas plant on Melkøya island, near Hammerfest in northern Norway. It is Norway's only seaborne LNG export plant, with capacity of roughly 4.3 million tonnes a year, and it liquefies gas from the Snøhvit field in the Barents Sea for shipment by tanker.
Norwegian pipelines carry far larger volumes into Europe, but Hammerfest gives the country a separate Arctic LNG route into The Atlantic cargo market. Its operating record therefore matters to buyers planning Europe's summer storage refill.
That record includes overruns. The plant's 2025 maintenance began on 22 April 2025 against a 10 July restart target, and a compressor fault pushed the return back by 24 days, to 3 August 2025. Its 2026 stops were far shorter: a valve fault in May, with restart set for 13 May, and planned maintenance on 13-16 June.
Hammerfest's 2026 stops lasted days
Hammerfest LNG's first stop of 2026 was unplanned. A valve fault halted the plant late on 8 May, and Equinor set a restart for 13 May. Planned maintenance followed in June: first scheduled for 8-11 June, the work moved to 13-16 June and took the plant out for three days.
Neither stop overlapped the late-May cut to Norwegian pipeline flows, which came from a compressor fault at the Troll A platform from 26 May. That sets the 2026 record apart from the plant's 2025 cycle, when maintenance that began on 22 April 2025 ran 24 days past its 10 July target and ended on 3 August 2025.
Is Hammerfest LNG still the largest LNG plant in Europe?
What is Hammerfest LNG and why does it matter for European gas?
Did Hammerfest LNG have maintenance problems in 2025?
Where is Hammerfest LNG and what does it produce?
What happened to Hammerfest LNG in 2025?
Why was Hammerfest LNG offline 2020-2022?
What is the capacity of Hammerfest LNG?
When did Hammerfest LNG go offline in 2025?
What is Hammerfest LNG?
Where does Hammerfest LNG get its gas from?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 28 September 2026. Editorial standards.