#12 29 Jul

Closed consultation on EirGrid's MPID 345 grid code modification

Data Centres: Boom and Backlash: Ireland writes the grid rules into contracts
#10 29 Jun
#7 16 Jun

Reopened large-load grid connections with 80% renewables within 6 years and 100% on-site backup conditions

Data Centres: Boom and Backlash: Irish regulators split over data centres
#2 27 Apr

Set December 2025 on-site-generation requirement that the Pure DC microgrid satisfies

Data Centres: Boom and Backlash: Pure DC Dublin microgrid surfaces as Irish template
#1 1 Apr

Pure DC's 110 MW Dublin microgrid skips queue