#1029 Jun
#716 Jun

Reopened large-load grid connections with 80% renewables within 6 years and 100% on-site backup conditions

Data Centres: Boom and Backlash: Irish regulators split over data centres
#227 Apr

Set December 2025 on-site-generation requirement that the Pure DC microgrid satisfies

Data Centres: Boom and Backlash: Pure DC Dublin microgrid surfaces as Irish template
#11 Apr

Pure DC's 110 MW Dublin microgrid skips queue

Data Centres: Boom and Backlash