IREN said on 5 November 2026 that network changes requested by Microsoft had delayed some deliveries at its 750 MW Childress campus, which carries a five-year US$9.7bn GPU contract, though it expects no penalties.
Last refreshed: 16 November 2026 · Appears in 1 active topic
Will Microsoft's network changes keep delaying IREN's Childress AI campus?
Background
Childress is a city of about 5,700 people and the seat of Childress County in north-West Texas, near the Panhandle.
IREN Limited runs a 750 MW data-centre campus on 576 acres in the city. The site carries IREN's five-year, US$9.7bn contract with Microsoft, signed in November 2025, to supply Nvidia GB300 capacity from four Horizon deployments totalling 200 MW. IREN delivered the first, a 50 MW liquid-cooled deployment, in August 2026.
On 5 November 2026 IREN said network-design changes requested by Microsoft, along with supplier timing, had pushed back some deliveries; it does not expect financial penalties. The campus sits in a state tightening its grip on large loads, after Governor Greg Abbott ordered an audit of every data centre in the Texas interconnection queue in August 2026.
What is IREN building in Childress, Texas?
Why were IREN's Microsoft deliveries delayed?
Where is Childress, Texas?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 16 November 2026. Editorial standards.