Alberta Electric System Operator
AI-generated illustration
OrganisationCA

Alberta Electric System Operator

Alberta's grid operator, which capped new grid-connected large loads at 1,200 MW in June 2025.

As of November 2026, with the Alberta Electric System Operator rationing grid connections for large loads, data centres in the province are pairing with their own plants, such as the 1,494 MW one approved near Calgary on 17 November.

Last refreshed: 26 November 2026

Key Question

Why are Alberta data centres building their own power plants?

Timeline for Alberta Electric System Operator

#19 17 Nov

Alberta clears a plant Bill 42 would bar

Data Centres: Boom and Backlash
View full timeline →

Background

The Alberta Electric System Operator runs the province's electricity grid and its wholesale market. It plans transmission and decides how new customers connect.

Since June 2025 it has limited new grid-connected large loads to 1,200 MW in total. That ceiling sends developers who want more capacity towards generation of their own, built beside the load rather than drawn from the grid.

The Alberta Utilities Commission showed that route in practice on 17 November 2026, approving a 1,494 MW plant for a proposed data centre near Calgary. Bill 42, tabled the following day, would bar such plants from prime farmland and from land near homes, though projects already approved, this one included, are exempt. The operator's cap therefore shapes where Alberta's data centres build and what powers them.

Common Questions
What is the Alberta Electric System Operator?
The body that directs the operation of Alberta's power grid, runs its wholesale electricity market, plans transmission and connects customers to the grid.Source: https://www.aeso.ca/aeso/about-the-aeso/
Why did Alberta cap data centre grid connections at 1,200 MW?
The AESO said 1,200 MW was the most additional large load the grid could serve to 2028 without hurting reliability, when 29 projects seeking more than 16 GW wanted to connect.Source: https://www.aeso.ca/aeso/newsroom/aeso-announces-interim-approach-to-large-load-connections/
Who got Alberta's 1,200 MW data centre allocation?
Two projects signed load contracts: the GLDC load project for 970 MW and Keephills Data Centre Phase I for 230 MW.Source: https://www.aeso.ca/grid/connecting-to-the-grid/large-load-projects/
Why are Alberta data centres building their own power plants?
With the AESO's interim cap fully allocated, generation built beside the campus is the route to gigawatt scale. On 17 November 2026 the Alberta Utilities Commission approved a 1,494 MW plant for Beacon Data Centers' Indus site.Source: Alberta Utilities Commission