Alberta Electric System Operator
Alberta's grid operator, which capped new grid-connected large loads at 1,200 MW in June 2025.
As of November 2026, with the Alberta Electric System Operator rationing grid connections for large loads, data centres in the province are pairing with their own plants, such as the 1,494 MW one approved near Calgary on 17 November.
Last refreshed: 26 November 2026
Why are Alberta data centres building their own power plants?
Timeline for Alberta Electric System Operator
Alberta clears a plant Bill 42 would bar
Data Centres: Boom and BacklashBackground
The Alberta Electric System Operator runs the province's electricity grid and its wholesale market. It plans transmission and decides how new customers connect.
Since June 2025 it has limited new grid-connected large loads to 1,200 MW in total. That ceiling sends developers who want more capacity towards generation of their own, built beside the load rather than drawn from the grid.
The Alberta Utilities Commission showed that route in practice on 17 November 2026, approving a 1,494 MW plant for a proposed data centre near Calgary. Bill 42, tabled the following day, would bar such plants from prime farmland and from land near homes, though projects already approved, this one included, are exempt. The operator's cap therefore shapes where Alberta's data centres build and what powers them.
What is the Alberta Electric System Operator?
Why did Alberta cap data centre grid connections at 1,200 MW?
Who got Alberta's 1,200 MW data centre allocation?
Why are Alberta data centres building their own power plants?
Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.