Alberta bill to bar data centres from prime farmland and within 600 m of homes.

As of November 2026, Alberta Bill 42, tabled on 18 November, would bar data centres from prime farmland and within 600 m of homes, yet it exempts the 1,494-megawatt Calgary-area plant approved the day before.

Last refreshed: 26 November 2026 · Appears in 1 active topic

Key Question

Why does Bill 42 exempt the Calgary plant it would otherwise bar?

Timeline for Alberta Bill 42

#19 17 Nov

Alberta clears a plant Bill 42 would bar

Data Centres: Boom and Backlash
View full timeline →

Background

Bill 42 is an Alberta government bill setting where data centres and the power plants that feed them may be built. Nate Glubish, the minister of technology and innovation, introduced it in the legislature on 18 November 2026.

Bill 42 regulates land and distance. Data centres and their plants would be kept off prime farmland, and a data centre would have to sit at least 600 m from homes. Any project the Alberta Utilities Commission has already approved, or is still considering, is exempt.

The exemption decides the bill's first real effect. On 17 November 2026, one day before the bill appeared, the Commission approved a 1,494-megawatt plant for a proposed data centre near Calgary, a project of the kind the bill targets that now proceeds outside it. The bill has not passed.

Common Questions
When was Alberta's Bill 42 introduced?
Nate Glubish, Alberta's technology and innovation minister, introduced it on 18 November 2026. It has not passed.Source: Government of Alberta
Why is the Calgary data centre plant exempt from Bill 42?
The bill exempts projects the Commission has approved or is considering. The plant near Calgary was approved on 17 November, the day before the bill was tabled.Source: The Globe and Mail
How far must Alberta data centres be from homes under Bill 42?
At least 600 m for data centres of 10 MW or more, though municipalities could ask the Alberta Utilities Commission for an alternative setback.Source: Government of Alberta
What is Alberta's Bill 42?
The Energy, Environment and Utilities Statutes Amendment Act, 2026. It would bar power plants and data centres from Class 1 and 2 farmland and set a 600 m setback from homes.Source: Government of Alberta