Germany net-withdrew 459 GWh on 13 April

3 min read
09:28UTC

Four days into the injection season the EU's largest storage estate is still drawing down, not refilling.

TechnologyDeveloping
Key takeaway

Germany is still emptying, not filling, and cannot accelerate its way out later.

Bundesnetzagentur-fed AGSI+ data shows Germany recorded a net gas storage withdrawal of 459 GWh on the 13 April gas day, leaving national storage at 23.27%, fractionally below the 23.32% posted on 12 April 1. Four days into what should have flipped to sustained injection, the country's cavern network was still running a net draw.

German injection capacity is fixed at 4,274 GWh/day against 7,047 GWh/day of withdrawal; the asymmetry means the pipelines can empty the caverns faster than they can fill them. A late start is not recoverable by acceleration, only by running closer to the injection ceiling for longer, which leaves no headroom for the next supply shock.

The EU aggregate is still on pace against the reduced November target , but it is running on periphery injection while the anchor drifts. Bruegel's refill estimate assumed Germany at net-injection by mid-April; that assumption has not held.

For winter-26 gas portfolios, this is the only domestic data point on the calendar that matters as much as the Hormuz ceasefire call ; it is also the only one that cannot be hedged with a headline.

Deep Analysis

In plain English

Gas storage works like a giant underground tank that Europe fills during summer when demand is low, then draws down during winter when heating demand is high. By early April the heating season should be winding down and the refilling should have started. Germany has the biggest gas storage network in the EU, so its behaviour sets the pace for the whole bloc. On 13 April it was still drawing gas out (459 GWh net), not putting it in, even though the storage season officially began on 1 April. That is a problem because Germany's filling equipment can only push gas in so fast. A late start cannot be made up by filling faster later. The tank is already unusually empty at 23.27%, about half the level it would be at this time in a normal year.

Deep Analysis
Root Causes

Germany's storage deficit has two structural causes distinct from the current Hormuz crisis. First, the Nord Stream pipeline destruction in September 2022 removed roughly 55 bcm per year of German-destined capacity, forcing Germany onto spot LNG and Norwegian pipeline at premium prices and preventing the pre-winter fill rates achievable before 2022.

Second, Germany's cavern storage geology (predominantly salt caverns with fast-cycle capability) means its working gas volumes are disproportionately small relative to its consumption. France and Italy hold a higher share of depleted-field storage with larger working volumes; Germany's estate is sized for rapid response, not strategic reserve depth.

What could happen next?
  • Risk

    If Germany remains in net withdrawal through late April, EU aggregate storage will miss the trajectory required for 80% by November, even with the target reduced from 90% (ID:2355).

  • Consequence

    Industrial demand curtailment orders in Germany, the EU's largest manufacturing economy, would amplify Cefic's reported 37Mt capacity loss by depressing output further in chemicals, steel, and glass.

First Reported In

Update #2 · TTF EUR 42 as Russian LNG ban enters range

Gas Infrastructure Europe· 15 Apr 2026
Read original
Different Perspectives
Germany (Bundeskartellamt)
Germany (Bundeskartellamt)
Germany's Bundeskartellamt declined to open antitrust proceedings against SAP, the company disclosed on 30 July, in the same fortnight the Commission's EUR 890m DMA fine against Google approached its 21 September compliance deadline. A German software champion cleared domestic scrutiny while an American platform faces enforcement, in the same regulatory season.
United States (USTR)
United States (USTR)
Washington's Section 301 investigation into EU digital enforcement, opened 24 July, had produced no Federal Register docket as of 4 August, even as Dell and 1,008 Nvidia GB200 NVL4 accelerators sit inside the EU's own sovereignty-branded MeluXina-AI build. The absent docket and the American hardware inside a European sovereignty project pull the same relationship in opposite directions.
UK government
UK government
The UK's Sovereign AI vehicle took a nine-figure equity stake in chip startup OLIX on 30 July, its fifth deal since April, while the Cabinet Office's 27 July fact sheet named no accounting officer for the GBP 1.1bn AI Hardware Plan. Whitehall is buying equity rather than capacity, inside a department mid-rename to Business, Innovation, Science and Trade.
Luxembourg government
Luxembourg government
Luxembourg is covering half of the newly disclosed EUR 80m contract value for MeluXina-AI, EuroHPC's Grand Duchy build, with Dell Technologies confirmed as supplying 1,008 Nvidia GB200 NVL4 accelerators, a hardware detail absent from the earlier project description. The disclosure means Luxembourg's national co-funding buys a facility built on American silicon under a European ownership badge.
European Commission
European Commission
The Commission activated its Article 101 fining power on 2 August while the Article 70 register it must keep current still showed a 26 September 2025 footer and blank rows for Denmark, Finland and Hungary. It issued no comment, though Article 70 puts the publication duty on Brussels, not member states.
China's Ministry of Commerce
China's Ministry of Commerce
Spokesperson He Yadong said on 16 July that Beijing and the Netherlands should let firms settle the Nexperia dispute through consultation, after a Dutch ministerial visit to Beijing. The conciliatory tone contrasts with the confrontational US trade response to the same fortnight's DMA enforcement.