Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether **Microsoft**, **Alphabet**, **Amazon** and **Meta** preserve their raised 2026 capex guidance through the late-July Q2 earnings cycle now that OpenAI's compute commitment has been visibly trimmed.
From the 16 May briefing · Deadline: late-July
Whether **FERC** publishes the RM26-4-000 NOPR (Notice of Proposed Rulemaking) by end-June, and whether PJM's 18 May filing matches the language FERC accepted on 16 April.
From the 16 May briefing · Deadline: 18 May
Whether the 18-21 May Denver, Seattle and Minneapolis votes produce a majority of refusals, consolidating the municipal moratorium tier into a default posture.
From the 16 May briefing · Deadline: 21 May
Whether OpenAI's pivot to leased compute reroutes Q3 hyperscaler bookings toward **Equinix**, **Digital Realty** and other colocation operators, and whether Crusoe's Abilene inventory finds a second taker.
From the 16 May briefing
The **FERC RM26-4-000** order at end of June: whether it constrains or accelerates large-load interconnection, and how it treats behind-the-meter cost allocation
From the 6 May briefing · Deadline: end of June
Whether any second US state attempts a moratorium after the Maine veto, and whether the Sanders-Ocasio-Cortez federal proposal reaches a committee mark-up
From the 6 May briefing
The **TSJ Aragón** ruling on the Ecologistas en Acción challenge, the first European judicial test of a community data-centre case
From the 6 May briefing
Stargate UAE first-phase commissioning against the Q3 2026 target
From the 6 May briefing · Deadline: Q3 2026
GE Vernova Q2 backlog: any sign of demand revision, or a further extension of the 2030 slot stretch
From the 6 May briefing
Whether **Governor Janet Mills** signs, vetoes or lets the Maine moratorium lapse before the May 2026 decision window closes.
From the 26 Apr briefing · Deadline: May 2026
Whether **Ofgem** publishes its AI-demand consultation response this quarter, the document UK grid analysts treat as the most consequential of the year.
From the 26 Apr briefing
Whether **Synergy Research Group's** Q1 2026 hyperscale figures, due mid-May, confirm or break the $142 billion quarterly capex baseline.
From the 26 Apr briefing · Deadline: Q1 2026
Whether **EirGrid** and **ESB Networks** publish the CRU-mandated data centre connection process or formally explain its absence.
From the 26 Apr briefing
Whether **Stargate UAE** phase 1 commissions on its Q3 2026 schedule or joins the headline-to-ground gap.
From the 26 Apr briefing · Deadline: Q3 2026
Whether the **Tribunal Superior de Justicia de Aragón** admits the Ecologistas en Acción challenge for substantive hearing, setting a Spanish precedent.
From the 26 Apr briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- SignificantCorrected 22 Oct 2026We said
Existing data centres in Seattle keep their current connections and can expand under pre-moratorium rules. Only new proposals above 20 MVA are blocked.
What was trueExisting data centres can keep operating. An expansion exemption permits at most another 20 MVA at eligible existing facilities; larger expansions also face the pause.
- SignificantCorrected 22 Oct 2026We said
voted unanimously on 9 and 10 June to stop
What was truevoted unanimously on 9 June, with the mayor signing on 11 June, to stop
- SignificantCorrected 22 Oct 2026We said
The ordinance exempts Seattle's existing data centres, which may keep expanding under current rules, so the freeze bites only on new arrivals.
What was trueQualifying operating facilities can continue operating. Their expansion exemption is limited to an additional **20 MVA**, so larger expansions also fall under the moratorium.
- SignificantCorrected 22 Oct 2026We said
making the freeze legally binding rather than provisional
What was truewith the ordinance taking effect when the mayor signed on **11 June**
- SignificantCorrected 22 Oct 2026We said
voted **9 to 0** on **9 and 10 June** to enact
What was truevoted **9 to 0** on **9 June** to approve
- SignificantCorrected 22 Oct 2026We said
voted 9 to 0 on 9 and 10 June to enact
What was truevoted 9 to 0 on 9 June to approve
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9-0 on 9 and 10 June. The vote made its 365-day moratorium legally binding on new loads above 20 MVA
What was trueSeattle's City Council approved its 365-day moratorium 9-0 on 9 June. It took effect with the mayor's signature on 11 June and applies to defined data centres above 20 MVA
- SignificantCorrected 22 Oct 2026We said
Existing data centres are exempt and may expand under current rules.
What was trueOperating facilities may continue, but the expansion exemption is limited to an additional 20 MVA; larger expansions are subject to the moratorium.
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9 to 0 on 9 and 10 June to enact the 365-day moratorium it had introduced on 30 April, making the freeze legally binding.
What was trueSeattle's City Council approved the proposed 365-day moratorium by 9 votes to 0 on 9 June. The ordinance took effect with the mayor's signature on 11 June.
- MinorCorrected 22 Oct 2026We said
The CRU decision text had not been checked.
What was trueCRU2026145 and CRU2026145c confirm the scope, date and derogation route.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
The exact start date lacked primary confirmation.
What was trueCRU's approval letter confirms the effective date as 27 October 2026.
- MinorCorrected 22 Oct 2026We said
All non-compliant sites must seek an exemption.
What was trueOnly sites covered by MPID 345 need a derogation.
- MinorCorrected 22 Oct 2026We said
MPID 345 applies to large electricity users generally.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All Irish data centres need an exemption if they cannot comply.
What was trueMPID 345 applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek an exemption.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.