The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether **Microsoft**, **Alphabet**, **Amazon** and **Meta** preserve their raised 2026 capex guidance through the late-July Q2 earnings cycle now that OpenAI's compute commitment has been visibly trimmed.
From the 16 May briefing · Deadline: late-July
Whether **FERC** publishes the RM26-4-000 NOPR (Notice of Proposed Rulemaking) by end-June, and whether PJM's 18 May filing matches the language FERC accepted on 16 April.
From the 16 May briefing · Deadline: 18 May
Whether the 18-21 May Denver, Seattle and Minneapolis votes produce a majority of refusals, consolidating the municipal moratorium tier into a default posture.
From the 16 May briefing · Deadline: 21 May
Whether OpenAI's pivot to leased compute reroutes Q3 hyperscaler bookings toward **Equinix**, **Digital Realty** and other colocation operators, and whether Crusoe's Abilene inventory finds a second taker.
From the 16 May briefing
The **FERC RM26-4-000** order at end of June: whether it constrains or accelerates large-load interconnection, and how it treats behind-the-meter cost allocation
From the 6 May briefing · Deadline: end of June
Whether any second US state attempts a moratorium after the Maine veto, and whether the Sanders-Ocasio-Cortez federal proposal reaches a committee mark-up
From the 6 May briefing
The **TSJ Aragón** ruling on the Ecologistas en Acción challenge, the first European judicial test of a community data-centre case
From the 6 May briefing
Stargate UAE first-phase commissioning against the Q3 2026 target
From the 6 May briefing · Deadline: Q3 2026
GE Vernova Q2 backlog: any sign of demand revision, or a further extension of the 2030 slot stretch
From the 6 May briefing
Whether **Governor Janet Mills** signs, vetoes or lets the Maine moratorium lapse before the May 2026 decision window closes.
From the 26 Apr briefing · Deadline: May 2026
Whether **Ofgem** publishes its AI-demand consultation response this quarter, the document UK grid analysts treat as the most consequential of the year.
From the 26 Apr briefing
Whether **Synergy Research Group's** Q1 2026 hyperscale figures, due mid-May, confirm or break the $142 billion quarterly capex baseline.
From the 26 Apr briefing · Deadline: Q1 2026
Whether **EirGrid** and **ESB Networks** publish the CRU-mandated data centre connection process or formally explain its absence.
From the 26 Apr briefing
Whether **Stargate UAE** phase 1 commissions on its Q3 2026 schedule or joins the headline-to-ground gap.
From the 26 Apr briefing · Deadline: Q3 2026
Whether the **Tribunal Superior de Justicia de Aragón** admits the Ecologistas en Acción challenge for substantive hearing, setting a Spanish precedent.
From the 26 Apr briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- MinorCorrected 16 Nov 2026We said
A Metropolitan Development Commission committee voted 10-3 on 13 July 2026 to recommend the moratorium.
What was trueThe City-County Council's Metropolitan and Economic Development Committee cast the 10-3 vote (WFYI, 13/07/2026).
- MinorCorrected 16 Nov 2026We said
Red Eléctrica de España entity page: majority state-owned via SEPI
What was trueSEPI holds 20% of parent Redeia (Redeia shareholder page); entity 5364 background and two FAQ answers corrected via enrichment on 16/11/2026
- SignificantCorrected 16 Nov 2026We said
Charlotte entity page: Bank of America Stadium was a 2026 FIFA World Cup host venue
What was trueCharlotte was not one of the 11 US host cities for the 2026 World Cup; entity 7588 background, definition, search terms and quick facts corrected via enrichment on 16/11/2026
- MinorCorrected 14 Nov 2026We said
The regional leaders argued that the pause reflects OpenAI's US-first prioritisation rather than UK dysfunction.
What was trueThe cited source gives their argument as the region keeping its AI Growth Zone status and being "open for business". The only analyst quoted, Professor Richard Whittle, called the pause a warning about the UK's AI-infrastructure model.
- MinorCorrected 14 Nov 2026We said
North East Mayor Kim McGuinness and Nscale chief executive Bjoern Norda rejected the framing of the OpenAI pause.
What was trueThe cited source (ResultSense via Prolific North, 23 April 2026) attributes the pushback to the North East Combined Authority, Dynamo North East and the North East Chamber of Commerce. It names neither McGuinness nor any Nscale executive. No person called Bjoern Norda can be found; Nscale's chief executive is Josh Payne.
- MinorCorrected 8 Nov 2026We said
internal process notes published in the body
What was truenotes not for readers
- MinorCorrected 8 Nov 2026We said
internal process notes published in the body
What was truenotes not for readers
- MinorCorrected 22 Oct 2026We said
Amazon Web Services was the Amazon subsidiary that bought the former George Washington University site.
What was trueAmazon Data Services bought the site; AWS appears in the update through event 6435's historical comparison.
- SignificantCorrected 22 Oct 2026We said
Voted 9-0 on 9-10 June to enact a 365-day moratorium on new loads above 20 MVA
What was trueApproved a 365-day moratorium on defined data centres above 20 MVA by 9-0 on 9 June; the mayor signed on 11 June
- SignificantCorrected 22 Oct 2026We said
Enacted the 365-day data-centre moratorium 9-0 on 9-10 June
What was trueApproved the 365-day data-centre moratorium 9-0 on 9 June; the mayor signed on 11 June
- SignificantCorrected 22 Oct 2026We said
Seattle's 365-day freeze arrived five days after the Maine override failed
What was trueSeattle's proposed 365-day freeze followed the Maine override defeat
- SignificantCorrected 22 Oct 2026We said
when Seattle froze
What was truewhen Seattle proposed its freeze
- SignificantCorrected 22 Oct 2026We said
and that process is now unavailable until at least **30 April 2027**.
What was truebut the April proposal had not yet enacted a year-long freeze.
- SignificantCorrected 22 Oct 2026We said
Seattle's city council voted to pause new large data centre projects for one year
What was trueSeattle councilmembers proposed pausing new large data centre projects for one year
- SignificantCorrected 22 Oct 2026We said
Seattle freezes data centres for a year
What was trueSeattle proposes a year-long data-centre freeze
- SignificantCorrected 22 Oct 2026We said
Seattle's moratorium exempts everything already connected.
What was trueSeattle's moratorium permits existing operations, but its expansion exemption is limited to an additional 20 MVA at eligible facilities.
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9-0 on 9-10 June to make its 365-day moratorium legally binding on new loads above 20 MVA
What was trueSeattle's City Council approved its 365-day moratorium 9-0 on 9 June; it took effect with the mayor's signature on 11 June and covers defined data centres above 20 MVA
- SignificantCorrected 22 Oct 2026We said
The 9-0 ordinance exempts Seattle's existing data centres, which may keep expanding under current rules.
What was trueExisting facilities can keep operating, but the expansion exemption permits at most another **20 MVA** at eligible facilities.
- SignificantCorrected 22 Oct 2026We said
making the freeze binding rather than provisional
What was truewith the ordinance taking effect when the mayor signed on **11 June**
- SignificantCorrected 22 Oct 2026We said
voted **9 to 0** on **9 and 10 June** to enact
What was truevoted **9 to 0** on **9 June** to approve