AEP Ohio
Ohio electricity utility whose July 2025 tariff makes new data centres pay for most of their requested capacity.
Ohio regulators approved AEP Ohio's data-centre tariff on 9 July 2025, making new loads above 25 MW pay for at least 85% of the capacity they request for up to 12 years, after interest in central Ohio passed 30 GW.
Last refreshed: 16 November 2026
Should data centres pay for grid capacity they reserve but never use?
Timeline for AEP Ohio
Google to pay own power bill in Malaysia
Data Centres: Boom and BacklashMentioned in: Prime breaks ground on 240 MW Phoenix
Data Centres: Boom and BacklashBackground
AEP Ohio, a subsidiary of American Electric Power, distributes electricity across much of Ohio. In March 2023 it stopped signing new data-centre agreements in central Ohio after initial interest passed 30 GW.
The Public Utilities Commission of Ohio answered with an order on 9 July 2025. New data centres above 25 MW pay for at least 85% of their requested capacity for up to 12 years, with a four-year ramp-up and exit fees, and the order set a process to lift the central Ohio pause.
Trade press treated the order as a precedent for making large loads pay for the grid they reserve. Deals elsewhere now follow similar logic: in Malaysia, Google said on 4 November 2026 that it will pay for all the power its new campuses use and the cost of connecting them.
What is the AEP Ohio data centre tariff?
Why did AEP Ohio pause data-centre connections?
Who owns AEP Ohio?