A ministry in Denmark scrapped its Microsoft alternative without announcement and left millions unspent, the engineering weekly Ingeniøren reported on 27 October1. Christina Egelund, minister for research, education and digitalisation, told the public broadcaster DR that heavy reliance on a few American providers is "a fragility for Denmark and for Europe"2. The report sets the government's stated aim against a stalled delivery: the minister still names US dependence as a risk while one ministry has dropped its own way out.
Think Tank Europa's 10 November brief adds a power limit. Projects of every kind totalling 57 GW queue for connection to Denmark's grid, eight times Denmark's current peak electricity demand, with waits of up to ten years3. An emergency grid plan adopted in October puts most data centres in the lowest of four priority bands, so new Danish data centres, sovereign or American, wait behind other users for power.
In September Bruegel put Europe's computing shortfall down to slow permits, not money, and Denmark's queue is the grid form of that constraint. Denmark's existing sites already supply about 149% of what the country is estimated to need, by Think Tank Europa's indicative count4. Copenhagen proposes harmonised risk assessments and mutual recognition of cloud providers across the EU. Think Tank Europa expects the government's national data-centre strategy before the end of the year.