ACER's 6 May derogation opinions covered seven national regulators, and named Hungary and Slovakia among the EU member states most exposed at the TurkStream entry ahead of the 5 August code-application date.

EconomicDeveloping
Key takeaway

Hungary and Slovakia face a regulatory checkpoint on TurkStream entry from 5 August.

ACER, the Agency for the Cooperation of Energy Regulators, published opinions on 6 May covering derogation requests from seven national regulatory authorities (NRAs) on EU gas network code application at third-country interconnection points. The seven NRAs are Bulgaria, Estonia, Hungary, Italy, Lithuania, Slovakia and Spain. The codes apply from 5 August 2026.

ACER is the Ljubljana-based EU body that coordinates national energy regulators and enforces the recast REMIT (Regulation on Wholesale Energy Market Integrity and Transparency) wholesale market rules in force from 29 April . Network codes set the technical, balancing and transaction-reporting standards for cross-border gas; at a third-country entry, they bind the EU side only, which is the structural problem the derogations target.

ACER found that Hungary and Bulgaria had implemented the codes "to the maximum extent possible" pending neighbouring Russian and Turkish operators' simultaneous implementation. Hungary and Slovakia are the two EU member states most dependent on the TurkStream pipeline, which ran at roughly 41 mcm/day in April routing Russian gas through Turkey and the Balkans. The bottleneck on third-country TSO (transmission system operator) cooperation is therefore concentrated on the route already carrying the bloc's heaviest physical-supply political risk.

Final decisions sit with the European Commission. If derogations are granted, EU measurement, balancing and REMIT transaction-reporting standards do not bind at the TurkStream entry from August. For desks running cross-border positions through Hungarian and Slovak hubs, the 5 August date is now a discrete regulatory checkpoint.

Deep Analysis

In plain English

The EU has rules about how gas should be measured, balanced, and reported when it crosses international borders into Europe. These rules were designed to make the gas market transparent and prevent price manipulation. TurkStream is a pipeline that carries Russian gas through Turkey and the Balkans into Hungary and Slovakia. The problem is that Russia and Turkey, who run the pipeline on their side of the border, do not follow EU rules. Europe can only set rules for EU members, not for Russia or Turkey. ACER, the EU energy regulator, has now formally acknowledged this gap. Hungary and Slovakia, the countries that rely most on TurkStream, asked for an exemption from the rules they technically cannot enforce at the border. ACER has given its opinion; now the European Commission has to decide whether to grant the exemption.

Deep Analysis
Root Causes

The structural cause is the 2019 recast Gas Directive's provision exempting new pipelines from third-country operators from unbundling and network code requirements, the provision that Russia successfully used to seek and receive (initially, before later being reversed) regulatory carve-outs for Nord Stream 2.

TurkStream was built and operates under an expectation of permanent exceptionalism from the EU regulatory framework, because the regulatory framework as designed cannot compel third-country TSO compliance.

The 5 August 2026 application date creates the immediate pressure: REMIT 2.0's transaction reporting obligations and the network code balancing standards that ACER is now opining on were designed as a coherent package. If TurkStream's entry point operates outside REMIT-equivalent transaction reporting from August, positions crossing the Hungarian and Slovak entry hubs carry a measurement and audit gap that compliance functions at trading houses will need to account for.

What could happen next?
  • Risk

    If the Commission grants derogations without conditions, REMIT 2.0 transaction reporting standards will not bind at TurkStream's EU entry from 5 August, creating an audit gap for cross-border positions referencing Hungarian and Slovak gas hubs.

    Short term · 0.7
  • Consequence

    A denied derogation creates a compliance default at TurkStream entry from 5 August without any practical mechanism to force Russian-Turkish TSO cooperation, meaning the denied outcome is a regulatory fiction rather than an enforcement improvement.

    Short term · 0.8
  • Precedent

    The ACER opinion establishes TurkStream as the test case for how EU network code architecture handles permanent third-country route dependencies, with implications for any future non-EU interconnection that cannot be governed through EEA-adjacent bilateral frameworks.

    Long term · 0.82
First Reported In

Update #8 · Storage 34.3 as 12 May test nears; Hammerfest silent

ACER· 8 May 2026
Read original
Different Perspectives
Cefic and European industrial gas offtakers
Cefic and European industrial gas offtakers
Chemical manufacturers running at 62-68% utilisation face mandate-funded storage that secures volume at above-commercial prices without reducing gas costs. A EUR 35bn refill bill, if confirmed, flows back through regulated network tariffs, adding directly to industrial energy costs already named by BASF and INEOS as structural.
OIES and energy research institutions
OIES and energy research institutions
Bruegel and OIES have not published a revised refill cost model at EUR 47-51 TTF with sub-0.4 pp/day pace. The EUR 35bn mid-range is drifting into use as the operative sub-80% November consensus, and the 11 June ACER workshop is the next venue where EU-level storage instrument advocacy can surface.
Equinor upstream gas
Equinor upstream gas
The Troll A compressor fault removed 34.6 mcm/day, stacked on Hammerfest, yet TTF fell 8.1% on Iran news the same day. Norwegian supply disruptions carry no price premium while Hormuz dominates; Equinor's 31 May Troll restart is a first estimate and the 2025 Hammerfest compressor fault of the same class slipped 24 days.
German Economy Ministry and Bundesnetzagentur
German Economy Ministry and Bundesnetzagentur
Berlin confirmed on 20 May it will not introduce a summer injection-incentive scheme, leaving Germany as the EU's only major unincentivised market after the storage levy lapsed on 1 January 2026. Commercial injectors apparently used the 18 May EUR 50 spike to lock winter supply cost rather than book against a structurally negative strip.
CRE and French gas operators
CRE and French gas operators
CRE's 100% mandatory booking order funds French injection regardless of the inverted strip, providing the EU aggregate cover that masks Germany's gap. The French position is insulated from TTF price moves but exposed to CRE's annual renewal cycle, a political risk rather than a commercial one.
Amsterdam-Rotterdam gas trading desks
Amsterdam-Rotterdam gas trading desks
TTF's 8.1% crash on a deal headline despite 50-plus mcm/day of verified Norwegian outages settled the EUR 50 question: it is a diplomatic ceiling, not a floor, and the short EUR 50-strike summer position keeps paying until Iran resolves. EBN's price-insensitive mandate buying tightens the prompt but the EUR 233m budget cap is a known position risk.